Name and Location
Panda Sherman project, Texas, US.

Client
Panda Power Funds.

Project Description
The project involves the construction of a 758 MW natural-gas-fuelled, combined-cycle power plant in Sherman, Texas.

Panda has designed the Sherman generating station as a ‘quick-start’ power plant.

Power generation is expected to start within ten minutes of start-up, reaching full gas turbine power production within about 30 minutes.

The plant will use the latest, most advanced emissions-control technology, making it one of the cleanest, most efficient natural-gas-fuelled power plants in the US.

Value
Not stated.

Duration
The power plant will come on line in late 2015.

Latest Developments
Bechtel and Siemens Energy have been awarded the turnkey construction of the project.

As part of the contract, Siemens will provide the power island package, including the natural gas turbines, the steam turbine, waste heat recovery boilers, and instrument and control systems.

Bechtel will be responsible for the engineering and procurement of the balance of the plant, as well as the installation, construction and commissioning of the facility.

Key Contracts and Suppliers
Bechtel and Siemens Energy (turnkey construction contract).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Bechtel media contact, Sonia Taylor, tel +1 301 228 7809 or email Staylor4@bechtel.com.
Siemens media contact, Christian Stuart Wilson, tel +49 9131 18 4974 or
email christian_stuart.wilson@siemens.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.065 0.108s - 145pq - 2rq
Subscribe Now