Owendale scandium project, Australia

12th August 2016

By: Mariaan Webb

Creamer Media Contract Publishing Editor

  

Font size: - +

Name and Location
Owendale scandium project, central New South Wales, Australia.

Client
Platina Resources.

Project Description
A scoping study on the Owendale project supports the economic and technical viability of the project and includes the development of capital and operating cost estimates to about a 50% accuracy for a suitable processing facility.

The project hosts a total mineral resource of 25.9-million tonnes of scandium grading 380 parts per million (ppm) at a cutoff of 300 ppm, and contains a total in situ content of 15 100 t of scandium oxide.

The base case for the project is a simple, openpit mining operation that will mine about 50 000 t/y of ore for treatment and concentration on site to produce 30 t of scandium oxide at 99.9% purity.

Mining is expected to take place two to three times a year in small campaigns from shallow openpits.

The mining concept will involve conventional truck and shovel opencut mining, most likely located on a shallow, high-grade starter pit. Batch high-pressure acid leach (HPAL) autoclaves are required to produce the initial 30 t of scandium oxide.

The Owendale project gained significant impetus in January this year when it was identified that more than 90% of the accompanying platinum mineralisation in the Owendale ore was extracted using the HPAL processing technique. As a result, the project has the potential to become Australia’s first scandium producer with platinum credits.

Net Present Value/Internal Rate of Return
Not stated.

Value
Capital costs are estimated at A$73.5-million.

Duration
Not stated.

Latest Developments
Platina has started environmental studies, which form a major component of a feasibility study for the project. Environmental base line monitoring programmes and conceptual design documentation for initial stakeholder engagement are part of the new work programme for the feasibility study, which will also include technical, processing and marketing studies on Owendale.

Platina expects a full environmental impact statement and a mining lease application for the project to be completed within 12 months.

Key Contracts and Suppliers
SNC Lavalin (scoping study and mineral resource update), RW Corkery & Co (environmental studies).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Platina Resources, tel +61 7 5580 9094, fax +617 5580 9394 or email admin@platinaresources.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 
The Steel Tube Export Association of South Africa
Steel Tube Export Association of South Africa

The Steel Tube Export Association of South Africa was established to develop sustainable, internationally competitive carbon steel tube and pipe...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.057 0.903s - 148pq - 2rq
Subscribe Now