Ora Banda starts simplification of Davyhurst

10th May 2022

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Gold miner Ora Banda Mining has started Stage 1 of its operational reset plan (ORP) as part of its plans to consolidate operations, cut costs and focus on cash generation over the next two years.

The Stage 1 ORP is focused on achieving process plant stability at the 1.2-million-tonne-a-year Davyhurst gold project, in Western Australia, and to streamline its openpit mining operations through rationalising earthmoving equipment by concentrating on mining at the Missouri openpit.

Stage 2 of the ORP will focus on resource development and sustainable mine production beyond the 24-month period of Stage 1.

Ora Banda in April this year announced that it would cease work at the Riverina openpit mine in order to focus on the Missouri deposit for the next six months. Operations at Riverina ceased on May 3, and ongoing rehabilitation work at the site is scheduled to be completed next week.

Ora Banda told shareholders on Tuesday that the move had allowed the company to reduce staffing and contractor labour requirements, which was expected to deliver significant cost savings.

Furthermore, the switch to single mine production had been positive for Missouri, as manning strength, which Ora Banda noted had been a challenge given the current labour shortages in Western Australia, had increased from as low as 80% to over 100% of baseline for the first time in the project’s life.

Meanwhile, effort is also continuing to increase the crushing circuit performance at the processing plant, through improved operational and preventative maintenance, while also reducing plant downtime through improved operational and preventative maintenance practices.

“These changes are all about simplifying Davyhurst so it has less working parts, a more affordable cost base and to give ourselves the ability to properly resource those parts of the business that need it most,” said interim CEO Andrew Czerw.

“We are confident that in the months ahead, these changes will move Ora Banda into a much stronger, cash accretive position.”

In the month of April, the Davyhurst process plant treated 92 784 t of ore for 5 427 oz of gold. This was a 5% throughput improvement on the previous month.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.049 1.039s - 140pq - 2rq
Subscribe Now