Oposura zinc/lead/silver project, Mexico
This article has been supplied.
Name of the Project
Oposura zinc/lead/silver project.
Location
The project is located in Sonora, Mexico.
Client
Azure Minerals.
Project Description
A scoping study has confirmed the Oposura project as economically and technically robust and high-margin. It states that the most suitable and economical mining methods comprise low-unit cost, openpit and room-and-pillar underground extraction methods.
The optimal mining rate will be about 500 000 t/y from a combination of openpit and underground mining operations, at life-of-mine (LoM) average grades of 4.6% zinc, 2.6% lead and 15.9 g/t silver, delivering an initial LoM of 5.3 years.
The processing flowsheet comprises two-stage crushing followed by ore sorting using dense-medium separation to reject waste material and feed an upgraded product to the milling and flotation circuit at an estimated 300 000 t/y at LoM average grades of 7.5% zinc, 4.1% lead and 24.5 g/t silver.
The plant will produce about 35 000 t/y of zinc concentrate and 16 000 t/y of lead concentrate containing about 19 000 t of zinc and 10 000 t of lead. The yearly production of lead concentrate will contain an estimated 145 000 oz of silver.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of A$112-million and an internal rate of return of 76%, with a payback of about 16 months.
Value
Preproduction capital is estimated at A$69.9-million, including capital contingency of 25%.
Duration
First production is expected in late 2020 or the first quarter of 2021.
Latest Developments
Azure aims to complete the prefeasibility and definitive feasibility studies by the end of 2019. Additional infill drilling to convert inferred resources to indicated resources has started and is expected to be completed by the end of 2018.
Azure is also completing its marketing exercise to obtain contract terms for its zinc and lead/silver concentrates.
Key Contracts and Suppliers
CSA Global (mine design and sequencing).
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Azure Minerals, tel +61 8 9481 2555, fax +61 8 9485 1290 or email admin@azureminerals.com.au.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation