Operational Improvements At Penumbra Coal Mine

17th September 2013

By: Creamer Media Reporter

  

Font size: - +

Continental coal  (0.06 MB)

Continental Coal Limited (“Continental” or “the Company”) the South African thermal coal production, development and exploration company, is pleased to announce various operational improvements at its recently commissioned Penumbra Coal mine.

Production build-up at Penumbra is on target to achieve its design capacity of 63,000 tonnes run-of mine (“ROM”) per month by November 2013. ROM production for July and August 2013 increased to an average of 26,787 tonnes per month, a 35% improvement over the average monthly production of 19,895 tonnes per month achieved in Q2 2013.

The commissioning of the permanent ventilation shaft in August 2013 was the last remaining infrastructure required to reach the design capacity of 63,000 tonnes per month. With adequate ventilation in place since early September 2013 both continuous miner sections were fully operational and able to establish the planned mining outlay of 9 road production sections. ROM production for September 2013 already exceeds 20,000 tonnes and is trending towards the planned 40,000 tonnes for the month. Achieving the planned production for September 2013 will also alleviate logistical congestion around the main conveyor and lay a sound foundation for the planned 50,000 ROM tonnes planned for October 2013.

Another positive development is the improvement in the yield as the mining sections are being established. The average yield for the month-to-date September 2013 is approximately 59%, a marked improvement on the average yield of 44% achieved in July and August 2013 and the average yield of 37% achieved in Q2 2013.

A drill-and-blast section will be added to the two continuous miner sections during November 2013 which will add additional flexibility to maintain the planned production rate. Each continuous miner section currently has two shuttle cars with the third cars expected in December 2013, creating further flexibility for steady state production.

All required surface infrastructure have been completed and the installation of the underground substations is now in progress. The installation of the substations has no impact on the planned production rate.

Commenting on progress made at Penumbra, Continental Chief Executive Officer, Mr Don Turvey said:

“We are delighted with the significant progress made at Penumbra in such a short time. We had to hold back on production due to ventilation constraints up to the end of August 2013 but the successful commissioning of the ventilation shaft will now allow us to move towards full design capacity. The team has already taken the production step change now that they have been unleashed and will reach steady state production by November 2013. The Penumbra project is further establishing itself as a model project from design, through development and now aiming for steady state production. Experience gained during the Penumbra project execution will stand us to good use when we commence development of De Wittekrans in the near future.”

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.049 1.068s - 143pq - 2rq
Subscribe Now