Nova nickel project, Australia
Name of the Project
Nova nickel project.
Location
Australia.
Client
Independence Group.
Project Description
A definitive feasibility study (DFS) on the Nova project has indicated the project as technically low risk and it can be highly profitable in less than two years. The outcomes of the DFS are remarkably consistent with those of the scoping study.
Nova has a maiden probable ore reserve comprising 13.1-million tonnes grading 2.1% nickel, 0.9% copper and 0.07% cobalt for a contained 273 000 t of nickel, 112 000 t of copper and 9 000 t of cobalt.
The planned mine is based on a 1.5-million-tonne-a-year underground operation with decline access. The principal stoping method will be sublevel open stoping (SLOS), with paste fill to maximise extraction. An estimated 83% of the planned production will be from sublevel open stoping, with the remaining 17% of production from the long-hole echelon retreat stoping method.
The SLOS stopes will measure up to 25 m x 25 m horizontally and 70 m vertically, containing up to 200 000 t of ore per stope.
The life-of-mine-plan includes 7% dilution, of which 5% is modelled at a dilution grade of 0.2% nickel. Stope ore recovery is calculated to be 95%, with development ore recovery being 100%.
The stopes will be backfilled using paste fill, produced from low-sulphur flotation tailings recycled from process-plant waste material. Comprehensive paste-fill testwork indicates that high-strength paste backfill material can be successfully generated using Nova process tailings, and that a suitable paste fill can be produced to meet the requirements of the mine development.
Ore and waste will be hauled in 60 t underground trucks up a straight, one-in-seven gradient decline. The decline has been designed to allow for conveyor haulage to be retrofitted later if deemed appropriate.
Underground grade-control drilling will be from a hanging-wall drive established early in the development sequence. This will allow for all grade control drilling for the entire mine to be completed within 24 months. This hanging-wall drive will also be used for paste fill reticulation.
The processing plant will have a 1.5-million-tonne-a-year nameplate capacity and will use a conventional crushing process, with a primary crusher fed by a dedicated front-end loader from stockpiles. A mobile crusher has also been incorporated into the design as backup for the primary crusher. Grinding by an open-circuit semiautogemous mill will be followed by a ball mill in closed circuit with hydrocyclones.
The flotation flowsheet required to produce separate copper and nickel concentrates is an open circuit, based on roughing, cleaning and cleaner scavenging. The circuit will be replicated for copper and nickel circuits, and regrinding on particular streams will be used to increase liberation and recovery for both circuits.
Low-sulphur tailings will be sent to either a high-density polyethylene (HDPE) plastic-lined tailings storage facility (TSF) or to the paste plant. The TSF has a designed storage capacity to store the process tailings not used as paste fill for the underground mine and will also be used as a reservoir for initial mine dewatering water. The TSF design is an above-ground impoundment with a single perimeter embankment and it will be lined with a composite liner system comprising a clay layer and an HDPE layer.
A detailed flowsheet and plant design have been completed and the site layout has been finalised. The plant layout has been designed with expansion capability, should additional mineralisation be discovered or throughput be increased. The crushing, grinding and flotation circuits have been sized to allow for a range of material types with varying comminution and flotation characteristics to minimise the risk of bottlenecking.
Groundwater exploration, pump testing and modelling simulations have been completed around the Nova-Bollinger deposits. Results indicate that some dewatering of the mine environment will be required during mine development. This water will be stored in the TSF and is expected to provide sufficient water for the first two years of mining and processing operations.
Beyond this period, process water will be sourced from three water bores identified in other aquifers within 4 km of the planned mine. As a contingency, further groundwater resources exist within a 50 km radius of the project and are available for development.
A reverse osmosis plant will provide desalinated water for concentrate cleaning and drinking water.
The project has a ten-year mine life, subsequent to development.
Jobs To Be Created
Not stated.
Net Present Value/Internal Rate of Return
Not stated.
Value
The project has an estimated capital cost of A$473-million, including a A$22-million contingency.
Duration
Construction at the site is expected to start in early 2015.
The operation reached commercial production on July 1, 2017, with the mine and processing plant achieving production rates at or above nameplate capacity in the second half of 2018.
Latest Developments.
In its second year of production in 2019, Nova has achieved total production of 30 708 t of nickel, 13 693 t of copper, and 1 090 t of cobalt at a cash cost of A$2.07/lb nickel.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
The project has experienced some delays with regard to the processing plant, however, these issues have been overcome and the plant has transitioned to continuous operations.
Contact Details for Project Information
Independence Group, tel +61 8 9238 8300.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation















