https://www.engineeringnews.co.za

Nova nickel project, Australia

8th August 2014

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Nova nickel project, Australia.

Client
Sirius Resources.

Project Description
A definitive feasibility study (DFS) on the Nova project has indicated the project as technically low risk and highly profitable in less than two years since discovery. The outcomes of the DFS are remarkably consistent with those of the scoping study.

Nova has a maiden probable ore reserve comprising 13.1-million tonnes grading 2.1% nickel, 0.9% copper and 0.07% cobalt for a contained 273 000 t of nickel, 112 000 t of copper and 9 000 t of cobalt.

The planned mine is based on a 1.5-million-tonne-a-year underground operation with decline access. The principal stoping method will be sublevel open stoping (SLOS) with paste fill to maximise extraction. An estimated 83% of the planned production will be from SLOS, with the remaining 17% of production from the long-hole echelon retreat stoping method.

The SLOS stopes will measure up to 25 m × 25 m horizontally and 70 m in height, containing up to 200 000 t of ore per stope.

The life-of-mine-plan includes 7% dilution, of which 5% is modelled at a dilution grade of 0.2% nickel. Stope ore recovery is calculated to be 95%, with development ore recovery being 100%.

The stopes will be backfilled using paste fill, produced from low-sulphur flotation tailings recycled from process-plant waste material. Comprehensive paste-fill testwork indicates that high-strength paste backfill material can be successfully generated using Nova process tailings and shows that a suitable paste fill can be produced to meet the requirements of the mine development.

Ore and waste will be hauled in 60 t underground trucks up a straight, one in seven gradient decline. The decline has been designed to allow for conveyor haulage to be retrofitted at a later date if deemed appropriate.

Underground grade-control drilling will be from a hanging wall drive established early in the development sequence. This will enable all grade control drilling for the entire mine to be completed within
24 months. This hanging wall drive will then also be used for paste fill reticulation.

The processing plant will have a 1.5-million-tonne-a-year nameplate capacity and will use a conventional crushing process, with a primary crusher fed by a dedicated front-end loader from stockpiles. A mobile crusher has also been incorporated into the design as backup for the primary crusher. Grinding by open circuit semiautogemous mill will be followed by a ball mill in closed circuit with hydrocyclones.

The flotation flowsheet required to produce separate copper and nickel concentrates is an open circuit based on roughing, cleaning and cleaner scavenging. The circuit will be replicated for copper and nickel circuits.

Low-sulphur tailings will be sent to either a high-density polyethylene (HDPE) plastic-lined tailings storage facility (TSF) or to the paste plant. The TSF has a designed storage capacity to store the process tailings not used as paste fill for the underground mine and will also be used as a reservoir for initial mine dewatering water. The TSF design is an above-ground impoundment with a single perimeter embankment and it will be lined with a composite liner system comprising a clay layer and an HDPE layer.

A detailed flowsheet and plant design have been completed and the site layout has been finalised. The plant layout has been designed with expansion capability, should additional mineralisation be discovered or throughput be increased. The crushing, grinding and flotation circuits have been sized to allow for a range of material types with varying comminution and flotation characteristics to minimise the risk of bottlenecking.

Groundwater exploration, pump testing and modelling simulations have been completed around the Nova-Bollinger deposits. Results indicate that some dewatering of the mine environment will be required during mine development. This water will be stored in the TSF and is expected to provide sufficient water for the first two years of mining and processing operations.

Beyond this period, process water will be sourced from three water bores identified in other aquifers within 4 km of the planned mine. As a contingency, further groundwater resources exist within a 50 km radius of the project and are available for development.

A reverse osmosis plant will provide desalinated water for concentrate cleaning and drinking water.

The project has a ten-year mine life subsequent to development.

Net Present Value/Internal Rate of Return
Not stated.

Value
The project has an estimated capital cost of A$473-million, including a A$22-million contingency.

Duration
Construction at the site is expected to start early in 2015 with first nickel and copper concentrate expected in the first quarter of 2017.

Latest Developments
With discussions on financing and offtake discussions having progressed significantly, it is expected that these will be finalised before the receipt of all necessary statutory approvals. Therefore, the key determinant of the development timetable will be government approvals.

Meanwhile, the Nova exploration camp will be partially expanded to facilitate preconstruction readiness.

While Sirius’s immediate focus is on the permitting and development of the Nova nickel mine, it is also well placed to continue with an aggressive exploration programme. As a result, exploration is continuing around Nova, elsewhere in the Fraser Range and at the Polar Bear project. On the Nova tenement, a deep-penetration electromagnetic survey is under way to identify additional “near mine” mineralisation.

Infill drilling of existing inferred mineral resources and follow-up drilling of adjacent mineralised zones around the Nova and Bollinger deposits will also be undertaken as soon as underground drill positions are established for the grade-control drilling programme.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Sirius Resources, tel +61 8 6214 4200, fax +61 8 6241 4299 or email admin@siriusresources.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Latest News

SKAO director-general Prof Jessica Dempsey
The SKA Observatory has a new head
2nd June 2026 By: Rebecca Campbell

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.06 0.1s - 148pq - 2rq
Subscribe Now