Northeast grid reliability project, US
Name and Location
Northeast grid reliability project, New Jersey, US.
Client
PSE&G.
Project Description
The Northeast grid reliability project will upgrade PSE&G’s power service, in the northern part of New Jersey, from its current 138 kV service to 230 kV on existing overhead transmission lines to comply with requirements set by the PJM interconnection, the regional energy grid.
The project will upgrade an 80 km route of overhead transmission lines along existing PSE&G rights-of-way from Roseland, through West Caldwell, North Caldwell, Cedar Grove, Little Falls, Clifton, Bloomfield, Nutley, Belleville, North Arlington, Newark, Lyndhurst, Kearny and Jersey City.
The overhead transmission portion of the project includes new transmission towers all designed to withstand wind impacts of up to 169 km/h.
New 230 kV underground transmission circuits will also be installed in Jersey City and from PSE&G’s Bergen switching station, in Ridgefield, to its Athenia switching station, in Clifton.
The 4.82 km underground transmission circuit will also be installed in Jersey City from PSE&G’s Hudson switching station to its South Waterfront switching station. Additionally, a 24 km underground circuit will be installed through Ridgefield, Palisades Park, Ridgefield Park, Bogota, Hackensack, Maywood, Rochelle Park, Lodi, Saddle Brook, Garfield and Clifton. The project also includes the reconfiguration of PSE&G’s switching stations in Roseland, Clifton, Saddle Brook, Newark and Jersey City.
This project will help ensure reliable electric power for nearly one-million New Jersey businesses and residents that require increased electric capacity.
Value
The project is estimated at $907-million.
Duration
The project is expected to be completed in June 2015.
Latest Developments
None stated.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
PSE&G’s media hotline, tel +1 973 430 7734.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation