https://www.engineeringnews.co.za

Nolans neodymium-praseodymium project, Australia

29th September 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Nolans neodymium-praseodymium (NdPr) project.

Location
Northern Territory, Australia.

Client
Arafura Resources.

Project Description
Nolans is one of the most advanced rare earths development projects globally. The Nolans Bore resource is rich in NdPr – the key rare earths used in high-strength permanent magnets.

The project has total mineral resources estimated at 47-million tonnes at 2.6% rare-earth oxides using a 1% cutoff grade.

The ‘Nolans Development Report’ (NDR), which was released in September 2014, details Arafura’s plans to develop its wholly owned project.

It will entail building a mine, concentrator and rare earths intermediate plant, as well as related infrastructure, at the Nolans site.

The proposed mining operation will use conventional openpit truck and excavator mining methods, supplemented by drilling and blasting for ore and waste.

Pit optimisation studies have generated schedules showing a mine life of 25 years based on measured and indicated resources; and  a mine life of more than 40 years based on total resources. Dilution is estimated at 11.4% (plus 0.1% mining loss) and 15.7% (plus 0.2% mining loss).

According to the NDR, geotechnical inputs, including pit slope parameters, have been developed for pit optimisations and pit design. A series of pit shells has been produced and the detailed pit design will be completed for the definitive feasibility study (DFS).

A strategic mining schedule for the measured and indicated optimisation scenario is based on a maximum overall mining rate of ten-million tonnes a year to produce an average of 900 000 t/y of plant feed. The life-of-mine optimisation scenario is based on a maximum overall mining rate of ten-million tonnes a year to produce an average of one-million tonnes of plant feed each year.

Meanwhile, the project’s post-beneficiation flowsheet has changed from one complex, intended to be located at Whyalla, to a split configuration comprising a rare earths intermediate plant at the Nolans site and an offshore rare earths separation plant in an established chemicals precinct.

Sulphuric acid instead of hydrochloric acid will be used in the preleach circuit; the project no longer includes a chloralkali plant and hydrochloric acid recycle. It is no longer necessary to produce sodium hydroxide and hydrochloric acid on site, and the reduced quantities required will be imported to both processing complexes.

Beneficiation at the mine site will comprise crushing, grinding, magnetic separation and flotation to produce a blended concentrate.

The beneficiation flowsheet is defined with a high level of certainty and is ready to be progressed to DFS level.

Concentrate will be pumped through a slurry pipeline to a rare earths extraction plant at the Nolans processing site. Rare earths will be extracted from the concentrate through chemical processing to produce a high-quality rare earths intermediate product. This flowsheet is well developed, with some parts requiring limited confirmatory work to provide more detail for the certainty of the process. Detailed process design criteria, as well as equipment selection and sizing, have been undertaken.

Tailings, residue and radionuclide retention will be confined to the Nolans site.

Rare earths will be separated into the final rare-earth oxide products at the offshore rare earths separation plant using solvent extraction, followed by precipitation and calcination.

Arafura’s detailed research programme at Ansto, including minipiloting and rare earths separation trials, has delivered design parameters for upscaling to a production-scale installation and the corresponding mass balance and raw-material requirements.

Yearly production has been adjusted from 20 000 t to 14 000 t of rare-earth oxide equivalent.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an estimated net present value of A$2.045-billion after tax, with a 10% discount rate.

The project has an internal rate of return of 21.4% and an after-tax payback of capital in the fifth year of operation.

Value
Overall capital costs, including contingency, are estimated at A$1.43-billion.

Duration
The NDR envisages construction to start in mid-2016 and production in early 2019.

Latest Developments
Arafura Resources has reported that the mine life at its Nolans rare earths project could be extended beyond 30 years.

Mine planning work undertaken in advance of the DFS has established a mining inventory that could support a longer mine life.

The study has reported an inventory and strategic production schedules that could enable Arafura to produce 14 000 t/y of total rare-earth oxides, including 3 600 t/y of NdPr oxide, for more than 30 years. 

The project is expected to have a maximum mining rate of five-million tonnes a year for the majority of the mine life, with steady-state beneficiation plant feed rate estimated at 525 000 t/y for the first 11 years of operation.

The study has not taken into account about 21-million tonnes of inferred mineral resource, or nine-million tonnes of rare-earth mineralisation from which lower metallurgical recoveries are predicted using the high-phosphate metallurgical process being piloted.

The company has said that considering the abundance of phosphate-rich plant feed available, Arafura plans to prioritise this material for processing and recovery of NdPr.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Arafura Resources, tel +61 8 6210 7666, fax +61 8 9221 7966 or email media@arafuraresources.com.au.
 
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.055 0.704s - 145pq - 2rq
Subscribe Now