Name of the Project
Muga-Vipasca potash project.

Location
About 50 km to the south-east of Pamplona, Spain.

Project Owner/s
Highfield Resources.

Project Description
An update to the Muga-Vipasca feasibility study has reconfirmed the compelling economics of the project.

The mine plan is based on proven and probable ore reserves of 104.3-million tonnes grading 10.2% potassium oxide, which includes the abutting exploration target.

The plan proposes the delivery of about one-million tonnes a year of muriate of potash – Phase 1 and Phase will both produce 500 000 t/y – over a mine life of 30 years, comprising about 18 years of mine-life from ore reserves and 12 years from additional mineral resources and the exploration target.

Underground access will be by twin parallel declines from over a length of 2.6 km to a depth of about 350 m.

The West decline will be developed with a bolter-miner using continuous haulage systems to transport mined material to surface and the East decline with road-headers. The same type of equipment will be used to develop underground infrastructure, including workshops and service areas such as emergency evacuation chambers, pumping stations and electrical rooms.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an estimated net present value, at an 8% discount rate, of €1.89-billion an internal rate of return of 25%.

Capital Expenditure
Capital costs for Phase 1 have increased from €368-million to €398-million and Phase 2 from €206-million to 2 €209-million. Highfield believes that there is still some scope to optimise and reduce initial capital expenditure, for example by using contract mining.

Planned Start/End Date
The project expects construction to start in the first half of 2022.

Latest Developments
Highfield has said that it will continue to work with its financial adviser to secure an “appropriate” construction financing package for Phase 1 of the project.

Key Contracts, Suppliers and Consultants
IGAN Consulting Group (revised mine plan).

Contact Details for Project Information
Highfield Resources, tel +34 948 050 577 or email info@geoalcali.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.047 0.852s - 127pq - 2rq
Subscribe Now