PERTH (miningweekly.com) – The newly expanded Bauxite Hills mine, in Queensland, is expected to cost A$35.8-million, ASX-listed Metro Mining has reported.

The company on Wednesday announced the results of a bankable feasibility study (BFS), which was based on an initial 17-year mine life, with production to start at an initial rate of two-million tonnes a year by April 2018, ramping up to a steady-state of six-million tonnes a year over the first four years of operation.

The BFS estimated that the Bauxite Hills mine will deliver yearly earnings before interest, taxes, depreciation and amortisation of A$145-million, and would have a net present value after tax of A$601-million and an internal rate of return of 81%.

Life-of-mine revenue has been estimated at A$5.7-billion.

“The completion of the BFS is an enormous achievement for the company and a testament to MEC Mining, Metro’s project team and the quality of the project,” said Metro MD Simon Finnis.

“The BFS also confirms the benefits of acquiring Gulf Alumina, allowing one integrated development plan across both asset bases.”

With the addition of Gulf’s Skardon River project, Metro essentially doubled the mineral reserve at its Bauxite Hills mine, with the direct shipping ore (DSO) reserve now estimated at 96.5-million tonnes.

DSO resources were estimated at 128.8-million tonnes for the enlarged project, up from the previously defined 65.3-million.

The BFS results compared with a 2016 prefeasibility study, which estimated that a A$40.1-million capital investment could deliver four-million tonnes a year of bauxite over a mine life of 13 years.

Finnis on Wednesday said the low initial capital requirements estimated for the expanded Bauxite Hills mine reflected the strategic intent of Metro to fast-track first production with a four-year ramp-up to steady state production of six-million tonnes a year.

The planned production ramp-up will require further capital expenditure in the early years of the operational phase, and Finnis noted that a range of options were available to fund these costs, including leasing and use of contractors.

Meanwhile, while the BFS has been completed with a six-million-tonne-a-year production target, environmental approvals will allow for production of up to ten-million tonnes a year, with Finnis saying the company would continue to evaluate the benefits of increasing production further as it moved through the predevelopment and operational phases.

Metro has now started financing activities to ensure sufficient funding to develop the project and discussions have started with potential debt providers. Metro plans to source financing through a combination of debt and equity.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 0.948s - 140pq - 2rq
Subscribe Now