https://www.engineeringnews.co.za
Africa|Automation|Aveng|boilers|Building|Civils|Coal|Coal-fired Power Station|Construction|Design|Efficiency|ELB|Electrical|Engineering|Fire|Gas|Generator|Generators|Installation|Instrumentation|Materials Handling|Power|PROJECT|Repairs|Resources|Service|Services|Siemens|Switchgear|System|Systems|Technology|ThyssenKrupp|ThyssenKrupp Materials Handling|ThyssenKrupp-Materials-Handling|Transformers|Water|Equipment|Maintenance|Solutions|Environmental|Infrastructure
Africa|Automation|Aveng|boilers|Building|Civils|Coal|Coal-fired Power Station|Construction|Design|Efficiency|ELB|Electrical|Engineering|Fire|Gas|Generator|Generators|Installation|Instrumentation|Materials Handling|Power|PROJECT|Repairs|Resources|Service|Services|Siemens|Switchgear|System|Systems|Technology|ThyssenKrupp|ThyssenKrupp Materials Handling|ThyssenKrupp-Materials-Handling|Transformers|Water|Equipment|Maintenance|Solutions|Environmental|Infrastructure
africa|automation|aveng|boilers|building|civils|coal|coalfired-power-station|construction|design|efficiency|elb|electrical|engineering|fire|gas|generator|generators|installation|instrumentation|materials-handling|power|project|repairs|resources|service|services|siemens|switchgear|system|systems|technology|ThyssenKrupp|thyssenkrupp-materials-handling|thyssenkrupp-materials-handling-company|transformers|water|equipment|maintenance|solutions|environmental|infrastructure

Medupi power station project, South Africa – update

Image of Medupi power station

27th May 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Medupi power station project.

Location
Medupi is located on an 883 ha site in Lephalale, Limpopo, in South Africa.

Project Owner/s
State-owned power utility Eskom.

Project Description
Medupi will be the fourth-biggest coal-fired power plant and the biggest dry-cooled power station in the world. The power station will comprise six units with an installed capacity of 4 764 MW.

The planned operational life of the station is 50 years.

The power station will use high-tech supercritical boilers, which will operate at higher temperatures and pressures, compared with those of older boilers, thereby providing greater efficiency. Supercritical technology will result in more efficient use of natural resources, such as water and coal, and will have an improved environmental performance and footprint.

It is the first baseload coal-fired power station to be built in South Africa in more than 20 years and its delivery on schedule is viewed as critical.

The project is somewhat unique because Medupi is being built in reverse order – traditionally Eskom has always started building Unit 1 and ended with Unit 6. This new approach is the result of the rock agglomeration on the southern side of the site, which was excavated and reused for engineering fill on the northern side.

The project forms part of the utility’s integrated strategic electricity plan and is designed to be wet flue-gas desulphurisation (WFGD) ready.

Potential Job Creation
At the peak of its construction, the project employed more than 18 000 people on building activities and another 2 000 supporting employees on site.

Further, more than 4 600 artisans, technicians, engineers and managers have been formally trained by Eskom’s contractors.

Capital Expenditure
The capital cost of the project is R122-billion so far, and Eskom expects to spend in total under R135-billion on completion of balance of plant (BoP).

Planned Start/End Date
All six units’ construction and commissioning activities were completed by July 2021, after more than a decade under construction. The project started construction in 2007.

The first unit, Unit 6, was synchronised to the grid on March 2, 2015. It attained full power (796 MW) on May 26, 2015, and attained commercial operation on August 23, 2015.

Unit 5 was first synchronised to the national grid on September 8, 2016. It reached full power (796 MW) on December 17, 2016, and attained commercial operation on April 3, 2017.

Unit 4 was first synchronised to the national grid on May 31, 2017. It reached full power (796 MW) on June 19, 2017, and attained commercial operation on November 28, 2017.

Unit 3 was first synchronised to the national grid on April 8, 2018. It reached full power (796 MW) on May 16, 2018, and attained commercial operation on June 28, 2019. 

Unit 2 was synchronised to the national grid on October 7, 2018. It reached commercial operation status on November 12, 2019.

Unit 1 was synchronised to the grid on August 27, 2019. It reached commercial operation on July 31, 2021.

Latest Developments
Eskom has reported that it has implemented repairs and fixes to generation units 1 to 3 at the Medupi power station, and that the units are operating at full load, producing 720 MW of electricity each.

Unit 4, which was damaged in a generator explosion, after hydrogen (used to cool the shaft) mixed with air instead of carbon dioxide during a purging process, will be brought online in August 2024. The estimates to repair the damage is R2.5-billion.

Eskom has said that it will implement fixes to design flaws as it undertakes repairs of the unit.

Meanwhile, units 5 and 6 at the power station are operating at partial loads to ensure they meet emissions licence requirements.

Eskom will implement fixes and repairs to these units during routine maintenance shutdowns in future to bring them to full load.

Eskom has said that it is working with original-equipment manufacturers to fix the defects that are contributing to Medupi having much lower availability than the targeted 92% availability.

However, over the past year, the Medupi team has maintained units 1 to 3 above 85% availability, with Unit 1 exceeding the objective 92% availability and Unit 6 achieving 74.6% availability.

The key issues with the boiler plants include that the reheater spray flows exceed the boiler contractual requirements owing to poor evaporator heat absorbance, which results in a high furnace exit gas temperature.

A basic design to solve the challenges under low-load and transient conditions has been completed and implementation is expected to be done between June 2023 and December 2024, depending on outage availability.

All five generating units, barring the damaged Unit 4, will have their mills upgraded this year, starting in May, with the final Unit 6 mill expected to return to service in September.

The costs to repair defects are estimated at R300-million a unit.

Key Contracts, Suppliers and Consultants
Principal Contracts:
Parsons Brinckerhoff (execution partner); Roshcon (enabling civils); Rula Bulk Materials Handling (coal overland conveyor and ash dump conveyor); Mitsubishi Hitachi Power Systems Africa, or now MHI Power (boiler); Alstom S&E Africa (turbine); LP Services consortium (low-pressure services); Alula Water (water treatment plant); Karrena-Concor joint venture, or JV (chimneys and silos); MPS JV (main civils); Actom (electrical power installation and medium-voltage switchgear); General Electric (low-voltage switchgear system); Siemens (auxiliary transformers and generator transformers); Standby Systems (uninterruptible power supply); Alstom C&I (control and instrumentation); Honeywell Automation & Control Solutions South Africa (fire detection and access control); T-Systems (information technology (IT) and IT infrastructure); Siemens ACI Open Consortium (laboratory and analysers); Civcon/G4 JV (miscellaneous infrastructure and reservoirs); Basil Read (buildings, ash dump infrastructure, clarifiers and coal stockyard extension); NCI (diesel generators); thyssenkrupp Materials Handling (coal stockyard equipment); Clyde Bergemann Africa (dust handling and conditioning systems); ELB Engineering Services (terrace coal and ash); Aveng Grinaker-LTA (buildings phases 1 and 3); Nugen Technologies (nitrogen); Stefanutti Stocks/Mathomamayo JV (raw-water pumpstation and substation), WBHO (Excess Coal Stock Yard), Eskom Rotek Industries (Dust handling plant – completing scope) and Exxaro (coal supply).

Contact Details for Project Information
Eskom media desk, email mediadesk@eskom.co.za.

Edited by Creamer Media Reporter

Comments

Showroom

SMS group
SMS group

At SMS group, we have made it our mission to create a carbon-neutral and sustainable metals industry.

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.086 0.159s - 167pq - 2rq
Subscribe Now