Africa|Automation|Aveng|boilers|Building|Civils|Coal|Coal-fired Power Station|Construction|Contractor|Efficiency|ELB|Electrical|Engineering|Fire|Gas|Generator|Generators|Installation|Instrumentation|Materials Handling|Power|PROJECT|Resources|Services|Siemens|Switchgear|System|Systems|Technology|ThyssenKrupp|ThyssenKrupp Materials Handling|ThyssenKrupp-Materials-Handling|Transformers|Water|Equipment|Solutions|Environmental|Infrastructure
Africa|Automation|Aveng|boilers|Building|Civils|Coal|Coal-fired Power Station|Construction|Contractor|Efficiency|ELB|Electrical|Engineering|Fire|Gas|Generator|Generators|Installation|Instrumentation|Materials Handling|Power|PROJECT|Resources|Services|Siemens|Switchgear|System|Systems|Technology|ThyssenKrupp|ThyssenKrupp Materials Handling|ThyssenKrupp-Materials-Handling|Transformers|Water|Equipment|Solutions|Environmental|Infrastructure
africa|automation|aveng|boilers|building|civils|coal|coalfired-power-station|construction|contractor|efficiency|elb|electrical|engineering|fire|gas|generator|generators|installation|instrumentation|materials-handling|power|project|resources|services|siemens|switchgear|system|systems|technology|ThyssenKrupp|thyssenkrupp-materials-handling|thyssenkrupp-materials-handling-company|transformers|water|equipment|solutions|environmental|infrastructure

Medupi power station project, South Africa – update

28th May 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Medupi power station project.

Location
Medupi is located on an 883 ha site in Lephalale, Limpopo, in South Africa.

Project Owner/s
State-owned power utility Eskom.

Project Description
Medupi will be the fourth-largest coal-fired power plant and the largest dry-cooled power station in the world. The power station will comprise six units with an installed capacity of 4 764 MW.

The planned operational life of the station is 50 years.

The power station will use high-tech supercritical boilers, which will operate at higher temperatures and pressures, compared with those of older boilers, thereby providing greater efficiency. Supercritical technology will result in more efficient use of natural resources, such as water and coal, and will have an improved environmental performance and footprint.

It is the first baseload coal-fired power station to be built in South Africa in more than 20 years and its delivery on schedule is viewed as critical.

The project is somewhat unique because Medupi is being built in reverse order – traditionally Eskom has always started building Unit 1 and ended with Unit 6. This new approach is the result of the rock agglomeration on the southern side of the site, which was excavated and reused for engineering fill on the northern side.

The project forms part of the utility’s integrated strategic electricity plan and is designed to be flue-gas desulphurisation (FGD) ready.

Potential Job Creation
About 18 000 construction contractor employees and 2 000 supporting staff were employed at the peak of construction.

Capital Expenditure
In July 2016, Eskom officially updated its cost-to-completion estimates for Medupi. The State-owned utility reported that Medupi was now expected to cost R145-billion, rather than the earlier revised estimate of R105-billion.

The cumulative cost incurred on the project for the year ended March 31, 2019, was not available at the time of going to print.

Planned Start /End Date
Medupi was initially scheduled to be fully operational in 2013, but might only be completed in 2021.

The first unit, Unit 6, was synchronised to the grid on March 2, 2015. It attained full power (796 MW) on May 26, 2015, and attained commercial operation on August 23, 2015.

Unit 5 was first synchronised to the national grid on September 8, 2016. It reached full power (796 MW) on December 17, 2016, and attained commercial operation on April 3, 2017.

Unit 4 was first synchronised to the national grid on May 31, 2017. It reached full power (796 MW) on June 19, 2017, and attained commercial operation on November 28, 2017.

Unit 3 was first synchronised to the national grid on April 8, 2018. It reached full power (796 MW) on May 16, 2018, and attained commercial operation on June 28, 2019. 

Unit 2 was synchronised to the national grid on October 7, 2018. It reached commercial operation status on November 12, 2019.

Unit 1 was synchronised to the grid on August 27, 2019. The unit is expected to reach full commercial operation ahead of its scheduled deadline in November 2020.

Latest Developments
South Africa’s Deputy President David Mabuza has confirmed that Eskom’s Medupi power station will be fully operational by the end of 2021.

Key Contracts and Suppliers
Principal Contracts:
Parsons Brinckerhoff (execution partner); Roshcon (enabling civils); Rula Bulk Materials Handling (coal overland conveyor and ash dump conveyor); Mitsubishi Hitachi Power Systems Africa, or MHMPSA (boiler); Alstom S&E Africa (turbine); LP Services consortium (low-pressure services); Alula Water (water treatment plant); Karrena-Concor joint venture, or JV (chimneys and silos); MPS JV (main civils); Actom (electrical power installation and medium-voltage switchgear); General Electric (low-voltage switchgear system); Siemens (auxiliary transformers and generator transformers); Standby Systems (uninterruptible power supply); Alstom C&I (control and instrumentation); Honeywell Automation & Control Solutions South Africa (fire detection and access control); T-Systems (information technology (IT) and IT infrastructure); Siemens ACI Open Consortium (laboratory and analysers); Civcon/G4 JV (miscellaneous infrastructure and reservoirs); Basil Read (buildings, ash dump infrastructure, clarifiers and coal stockyard extension); NCI (diesel generators); thyssenkrupp Materials Handling (coal stockyard equipment); Clyde Bergemann Africa (dust handling and conditioning systems); ELB Engineering Services (terrace coal and ash, dust handling plants); Aveng Grinaker-LTA (buildings phases 1 and 3); Nugen Technologies (nitrogen); Stefanutti Stocks/Mathomamayo JV (raw-water pumpstation and substation) and Exxaro (coal supply).

Contact Details for Project Information
Eskom media desk, email mediadesk@eskom.co.za.

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Comments

Showroom

Goodwin Submersible Pumps Africa (Pty) Ltd
Goodwin Submersible Pumps Africa (Pty) Ltd

Goodwin Submersible Pumps Africa is sole distributors for Goodwin electrically driven, submersible, abrasion resistance slurry pumps.

VISIT SHOWROOM 
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.091 0.181s - 167pq - 2rq
Subscribe Now