Mbeya coal-to-power project, Tanzania
Name and Location
Mbeya (formerly Rukwa) coal-to-power project (MCPP), Tanzania.
Client
Kibo Mining.
Project Description
The project comprises two prospecting licences and two prospecting licence applications in south-western Tanzania, just south of Lake Rukwa.
The MCPP is expected to deliver 109-million tons of thermal coal over its mine life, with the coal to be fed into a 250 MW to 300 MW mine mouth thermal power station.
Stage 1 of the project comprises the completion of a bankable feasibility study on the coal mine and a prefeasibility study (PFS) on the power plant by December 2014.
Stage 2 will comprise all development and construction activities relevant to the mine and the power plant, with Stage 3 encompassing the commissioning and operation of the Mbeya coal mine and the Mbeya power station.
Net Present Value/Internal Rate of Return
Not stated.
Value
The project is estimated at $760-million.
Duration
Not stated.
Latest Developments
Kibo has reported that it can now “significantly increase” the pace at which feasibility work at its MCPP can be concluded, after construction and engineering company Chinese Shandong Electric Power Construction Corporation III’s (Sepco III’s) board approved a joint development agreement.
The agreement will also increase its ability to secure more investors and finance for MCPP.
The board approval has paved the way for Sepco III to make an equity investment in the MCPP, to a maximum of 15% of total equity in the special purpose vehicle that will ultimately hold the MCPP asset, while Kibo will hold the remaining 85%.
This investment will be made towards the completion of the definitive feasibility study (DFS) in October. Sepco III will also retain specific responsibility to lead the power generation component of the DFS and Kibo will lead the mining component.
The partners will also collaborate on identifying and reviewing construction providers and power plant operators to build and operate the completed MCPP and the appropriate financing structure for the MCPP construction process.
In addition, the DFS work will include negotiation and agreement of the terms of a power purchase agreement, implementation agreement and environmental-impact assessment.
Key Contracts and Suppliers
Standard Bank (financial adviser).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Kibo Mining, tel +353 91 865367, fax +353 91 755066 or email info@kibomining.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation