Makhado hard coking and thermal coal project, South Africa

26th March 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Makhado hard coking and thermal coal project.

Location
Limpopo, South Africa.

Project Owner/s
Emerging developer and producer of high-quality thermal and coking coal MC Mining (93.3%).

The Industrial Development Corporation (IDC) of South Africa currently has a project-level interest in the Makhado coal project of 6.7%.

Project Description
Makhado is classified as an evaluation asset and has not historically been mined.

The project will be completed in two phases.

Phase 1 will start with the development of Makhado’s west pit, producing three-million tonnes a year run-of-mine (RoM) coal. The coal will be mined by an independent mining contractor using truck-and-shovel, modified terrace mining methods.

RoM coal will be partially beneficiated before being dispatched to MC Mining’s Limpopo Coal Company subsidiary’s modified Vele colliery for processing. About two-million tonnes a year of RoM coal (ex-discard) will be trucked to Vele for processing at the colliery’s enhanced plant. Plant modifications include a new fines circuit comprising a reflux classifier, in series with the existing spiral plant, a low-density secondary wash plant and a froth flotation plant to capture the ultrafine coal.

At steady state, the operation will produce 1.1-million tonnes of saleable coal – 540 000 t/y of hard coking coal and 570 000 t/y of 5 500 kcal thermal coal.

The saleable coal will be trucked to the Musina siding for railing to domestic and/or export clients.

Phase 1 is a critical step in the development of Phase 2 of the Makhado project.

Phase 2 involves the implementation of the Makhado Lite plan, which will produce about 1.7-million tonnes a year of saleable coal comprising 700 000 t/y to 800 000 t/y of hard coking coal, and between 900 000 t/y and one-million tonnes a year of thermal coal. The project involves the development and mining of the east and west pits, the Makhado processing plant and associated infrastructure.

The entire Makhado project has a minimum life-of-mine of 46 years.

Potential Job Creation
Phase 1 mining and processing will be outsourced to experienced third parties that have previously operated in South Africa, and is expected to create about 650 permanent employment opportunities.

Net Present Value/Internal Rate of Return
Phase 1 has an estimated internal rate of return of more than 45%, with a payback of 2.5 years.

Capital Expenditure
Phase 1 will cost about R700-million.

Planned Start/End Date
The construction of the Phase 1 pit, including plant and infrastructure, is planned to take nine months, with the first coal sales in month ten.

The Phase 2 east and central pits are proposed to be developed in about 2023.

Latest Developments
The project has all the regulatory permits required to develop the project and start mining.

Key Contracts, Suppliers and Consultants
Minxcon (competent person’s report).

Proposals for full mining services have been sourced from various contract mining companies, with turnkey processing plant construction and operating quotes obtained from potential service providers.

Contact Details for Project Information
MC Mining, tel +27 10 003 8000, fax +27 11 388 8333 or email adminza@mcmining.co.za.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.048 0.864s - 127pq - 2rq
Subscribe Now