https://www.engineeringnews.co.za

Mahenge graphite project, Tanzania

6th September 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Mahenge graphite project.

Location
South-east Tanzania.

Project Owner/s
Black Rock Mining.

Project Description
Mahenge will be an openpit mining operation based on mining the Ulanzi and Cascade deposits using a conventional truck-and-shovel method.

The deposit is the fourth-biggest Joint Ore Reserves Committee-compliant contained graphite resource in the world.

The project has a mineral resources estimate of 212-million tonnes grading 7.8% total graphitic carbon (TGC) for more than 16-million tonnes of contained graphite.

Total proven and probable reserves are estimated at 70-million tonnes grading 8.5% TGC.

In July 2019, Black Rock released an enhanced definitive feasibility study (DFS) on the project.

Ore will now will be processed using a four-module approach over 26 years, a decrease of the life-of-mine (LoM) estimated in the DFS of 32 years. Total LoM production has increased from 6.6-million tonnes in the DFS to 7.4-million tonnes in the enhanced DFS.

Mining will be undertaken using conventional opencut techniques.

Processing will be undertaken using well-proven crushing, grinding and flotation methods, comprising:

Module 1, will include a processing plant and infrastructure at a nominal design basis rate of one-million tonnes a year to produce up to 83 000 t/y of graphite concentrate in the first two years of production. The plant will be based at the Ulanzi pit.

Module 2, which will include a second one-million-tonne-a-year plant and associated additional infrastructure, doubling throughput to two-million tonnes a year, and graphite concentrate production to 167 000 t/y from Year 3 of operation.

Module 2 includes some shared equipment with Module 1. The plant will be based at the Ulanzi pit.

Module 3, which will include a third one-million-tonne-a-year plant and associated additional infrastructure, increasing throughput to three-million tonnes a year, and graphite concentrate production of up to 250 000 t/y from Year 3 of operation.

Module 4, which will produce an additional 85 000 t/y of graphite concentrate, increasing total steady-state production to between 340 000 t/y to 350 000 t/y of graphite concentrate.

The additional mill feed in the enhanced DFS will be sourced by developing a third pit at the Epanko deposit.

Epanko ore is exclusively scheduled into Module 4, with production starting at Year 7 in the compressed schedule.

Epanko will contribute 9.9-million tonnes at 6.7% TGC for an additional 660 000 t of concentrate

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The projected after-tax net present value of the project has increased by 30%, from $895-million in the DFS to $1.16-billion in the updated DFS, with the internal rate of return having increased from 42.8% to an estimated 44.8%.

Capital Expenditure
Total capital expenditure for all four modules is estimated at $337-million.

Module 1 capital costs have increased from the $115-million estimated in the original DFS to $116-million in the updated DFS.

Module 2 capital costs are estimated at $69.5-million.

Module 3’s capital costs have increased marginally from $84.2-million in the DFS to $85.3-million in the enhanced DFS.

Module 4 will cost $67.1-million.

The $222-million required to find modules 2, 3 and 4 will be funded from internal cash flow.

Planned Start/End Date
First production from Mahenge has been targeted for between 2020 and 2021, with the timing of the first production subject to finance.

The enhanced DFS has noted that the development schedule, subject to financing and confirmation of the Tanzania government’s 16% free carried interest, will consider four production modules, one a year after the first module, rather than every two years as indicated in the DFS.

Latest Developments
Black Rock Mining has improved the economics of its Mahenge graphite project, with the addition of a fourth production module.

The addition of the fourth module is in response to customer demand for a more aggressive ramp-up of the Mahenge project.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Black Rock Mining, tel +61 8 9320 7550 or email info@blackrockmining.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.05 0.747s - 147pq - 2rq
Subscribe Now