Lusaka transmission and distribution rehabilitation project, Zambia

29th May 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Lusaka transmission and distribution rehabilitation project, Zambia.

Client
Zambia Electricity Supply Commission (Zesco).

Project Description
Lusaka’s electricity demand has grown at 6% a year over the past ten years, with demand now outstripping the installed capacity of the power system supplying the city. The project will increase the capacity and improve the reliability of Lusaka’s electricity transmission and distribution system for the community, as well as ensure the long-term sustainable operation of the network.

The first phase will result in the rehabilitation of the 132 kV and 88 kV transmission network in the Lusaka area, which will include the upgrading of four transmission lines, constructing three new substations and replacing 11 kV switchgear in various locations.

The second phase will entail the rehabilitation of the 33 kV and 11 kV distribution network in the same area and will include constructing three new substations and upgrading existing substations.

The third phase will include technical assistance and project supervision.

Value
The project is funded by the World Bank and will cost an estimated $200-million to implement.

Phase 1 will cost $106-million, Phase 2 $94-million and Phase 3 $10-million.

Duration
The project is expected to be completed in 2019.

Latest Developments
Zesco has awarded Aurecon a contract to provide engineering, design and construction supervision services for the project.

Key Contracts and Suppliers
Aurecon (engineering, design and construction supervision services).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Zesco, tel +260 211 361111, fax +260 211 222753 or email zesco@zesco.co.zm.
Aurecon communications manager Jody Boshoff, tel +27 12 427 2066, fax +27 86 606 0671 or
email Jody.Boshoff@aurecongroup.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Latest News

SKAO director-general Prof Jessica Dempsey
The SKA Observatory has a new head
2nd June 2026 By: Rebecca Campbell

Showroom

Industrial Nozzles & Systems (Pty) Ltd
Industrial Nozzles & Systems (Pty) Ltd

Industrial Nozzles & Systems (Pty) Ltd (Est. 2000) exclusive representative in Southern Africa for LECHLER GmbH (Est. 1879) - Europe's leading...

VISIT SHOWROOM 
ATI Systems
ATI Systems

ATI systems comprises five divisions: electrical assemblies, drives and controls, feedback sensors, enclosures, and strip guiding.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 1.143s - 145pq - 2rq
Subscribe Now