Lundin Gold about to transition from developer to producer

11th November 2019

By: Mariaan Webb

Creamer Media Contract Publishing Editor

     

Font size: - +

Vancouver-headquartered developer Lundin Gold is about to transition to a producer, with the Fruta del Norte project, in Ecuador, set to deliver its first gold before the end of this year.

The company has reaffirmed its production goal for the current quarter, after protests last month temporarily impacted on the movement of supplies and personnel to the project site.

The 310 000-oz/y Fruta del Norte will achieve commercial production in the second quarter of next year, Lundin Gold reported in its September quarter results announcement on Friday.

However, two permits are required before operations could begin and the company said that it expected to receive them “shortly”.

Lundin stated in its quarterly report that overall construction was about 89% complete, underground development was ahead of projections and that about 148 000 t of ore had been stockpiled by the end of September.

“I want to congratulate our team on achieving two major project milestones: hot commissioning of the process plant is under way and the recent energisation of the powerline,” said president and CEO Ron Hochstein.

The process plant wet commissioning started early in the third quarter and hot commissioning began towards the end of the quarter with first ore put through the grinding mills on September 27.

Lundin said that hiring for operations continued to progress on plan with less than 100 positions open at quarter-end, with the majority expected to be filled from existing project staff.

At the end of September, about 46% of the company’s employees and 45% of all workers, including contractors, were from the Zamora Chinchipe province.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 0.953s - 140pq - 2rq
Subscribe Now