Name of the Project
Leonora gold project (LGP).

Location
The project is located in the North-Eastern goldfields of Western Australia.

Client
Kin Mining.

Project Description
A definitive feasibility study (DFS) has confirmed that the LGP is technically sound and highly profitable.

The LGP boasts indicated and inferred resources of 22.3-million tonnes grading 1.4 g/t gold for 1.02-million ounces of contained gold, and a maiden ore reserve of 7.9-million tonnes grading 1.5 g/t for 373 000 oz.

Development is based on three openpit mining centres:
• Cardinia (mainly oxide and transitional ores), which comprises the Bruno-Lewis Link, Lewis, Kyte, Helens and Rangoon deposits;
• the Mertondale area, which comprises the Mertons Reward (transitional and fresh ores), Mertondale 3-4 (oxide, transitional and fresh ores) and Tonto (transitional ore); and
• the Raeside deposits of Michelangelo and Leonardo (transitional and fresh ores).

These deposits will supply a 1.5-million-tonne-a-year conventional carbon-in-leach (CIL) processing plant, centrally located at Cardinia.

Kin envisages that all mining will be undertaken by owner-miner operators using equipment supplied and maintained by a contract mining equipment supplier. 

All drill, blast and grade-control activities will be undertaken by contractors. Kin will provide all technical and managerial direction.

The mining strategy is focused on initially delivering oxide and transitional ore sourced primarily from the Cardinia deposits.

Mining operations will include the Mertondale pits in Year 3 and Raeside material in Year 4.

The DFS incorporates the refurbishment and upgrade of the 800 000 t/y Lawlers plant, acquired from Gold Fields this year, to 1.5-million tonnes a year through the installation of a refurbished 2.5 MW ball mill and six new 1 500 m3 CIL tanks. 

The proposed plant incorporates a two-stage crushing circuit feeding the ball mill, with gold extracted by gravity and CIL processes.

The DFS has determined that the LGP can produce an initial 61000 oz in its first full year of production, reaching maximum production of 65 000 oz in Year 7.

Potential Job Creation
The mine is expected to have a permanent workforce of about 64 people.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of A$107.4-million and an internal rate of return of 77%, with a preproduction payback of 11 months.

Value
The preproduction capital cost is A$35.4-million, which includes 18% in contingencies.

Duration
Plant commissioning and first gold are targeted for the second half of 2018.

Latest Developments
Kin Mining has exercised its option to buy a used 2.5 MW ball mill and new intertank screens and agitators for the CIL tanks at the Leonora gold project.

The company has bought the ball mill and CIL components from mining equipment company Maca-Interquip for A$1.27-million.

This purchase completes the acquisition of necessary key equipment required for the development of the Leonora gold project, where development is under way.

In addition to the essential drive train components, the ball mill comes with a spare motor, and a gearbox and pinion, along with engineering details that will serve to reduce installation costs. The ANI mill was last used at the Mount McClure gold operation in Western Australia and is in good condition.

The six intertank screens and agitators are unused and in new condition.

The installation of the 2.5 MW ball mill, which forms part of the upgrade of the Lawlers plant at Leonora, will provide single-stage primary grinding of the Cardinia ores at a yearly throughput rate of 1.5-million tonnes.

Refurbishment work can now start to ensure it can be installed according to the project’s development schedule.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Kin Mining, tel +61 8 9242 2227 or email info@kinmining.com.au.
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Axiom Hydraulics
Axiom Hydraulics

Axiom Hydraulics is a trusted leader in South Africa’s hydraulic industry, delivering world-class components, systems, and engineering expertise...

VISIT SHOWROOM 
MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.054 0.848s - 147pq - 2rq
Subscribe Now