Law firm warns of lack of pandemic risk clauses in public sector tenders, contracts

10th February 2021

By: Schalk Burger

Creamer Media Senior Deputy Editor

     

Font size: - +

After almost a year of dealing with Covid-19-related shutdowns and disruptions, public sector tenders and contracts still do not include any clauses that deal with the pandemic, construction and technology law firm MDA Attorneys said on February 10, following a review of the contract conditions of several tender packages posted for public sector work.

“The pandemic can no longer be deemed unforeseen and treated as a force majeure event, which is the provision most claims have relied upon during the significant disruptions of the past year. The ramifications are not only foreseeable, such as levels of lockdown, which restrict movement, but they can now be provided for in contracts and tenders,” says MDA Attorneys director Natalie Reyneke.

"Covid-19 is likely to continue to wreak havoc on South Africa’s construction sector for at least another year and parties need to be agile and prepared for further possible repercussions," she cautions.

The most common matters dealt with by MDA’s clients were identified and relevant clauses to deal with these issues were added to public sector tenders and contracts to cover works on site that were suspended or completely halted; border closures that affected the supply chain, materials and goods delivery; the restriction of movement requiring the demobilising of workers from sites and necessitating additional travel arrangements; and health and safety measures that had procedural and cost implications.

“Most of the public works tender documents we reviewed incorporated the General Conditions of Contract for Construction Works. Amendments to applicable laws and events that occur after commencement instructions are two areas of this contract that need to be adapted for Covid-19,” explains Reyneke.

"In view of the uncertainty surrounding the pandemic, parties who commission work (employers) may be faced with time and additional money claims from contractors."

Since Covid-19 and its potential impacts on the time and cost of a project have not been factored into the tender documents, we are advising our clients to include them as early as possible. A key issue to be agreed is whether pandemic-related issues should be a shared risk between both parties, says Reyneke.

"The clauses of a contract that should be amended are now much simpler to identify. They include delays and/or other events preventing performance, which will entitle a claim for extension of time with related costs, access, mobilisation, demobilisation to and from site, health and safety, price adjustment, escalation in supplier costs, types of insurances to be considered for proper cover relating to certain unforeseen events and the impact, as a result as well as termination of the contract."

Parties should carefully review the circumstances and expressly define Covid-19-related events as well as the entitlements to time and money that could be claimed by the contractor, warns Reyneke.

“The risks and circumstances differ for each project. Identify and research them and ensure your agreement includes  clear, balanced duties and responsibilities for efficient, cost-effective operations,” she advises.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.275 0.356s - 152pq - 2rq
Subscribe Now