Lace diamond mine development project, South Africa

29th May 2015

  

Font size: - +

Name and Location
Lace diamond mine development project, Free State, South Africa.

Client
Lace Diamond Mines (LDM), a 74% subsidiary of DiamondCorp.

Project Description
The 1.2-million-tonne-a-year Lace mine is expected to produce more than 500 000 ct/y of diamonds at peak production.

The Main pipe at Lace mine contains 33.1-million tons of kimberlite, indicated and inferred to a depth of 855 m, containing an estimated 13.4-million carats in both resource categories at an average grade of 40.1 ct per hundred tonnes (cpht).

The resource has an in situ value of more than $2-billion at $160/ct.

The deposit will be mined using block-cave mining, with three caves planned over the 25-year life-of-mine (LoM) on the 47, 67 and 85 levels at depths of 470 m, 670 m and 850 m respectively.

The kimberlite is open at depth, with a significant bulge between 250 m and 360 m. The kimberlite can potentially add additional tonnage and diamonds not currently included in the resource statement.

Net Present Value/ Internal Rate of Return
Not stated.

Value
The total development cost of the project, including working capital and a 15% contingency on capital and development costs, is estimated at R384-million.

The peak funding requirement of R286-million is expected in April 2015, when blasting of the slot drive and doming will start to deliver significant tonnages of kimberlite.

The costs of establishing the block cave thereafter are offset by revenues from the sale of diamonds, recovered from kimberlite mined during development.

Duration
The Lace mine is due to start production in the second half of 2015.

Latest Developments
DiamondCorp says development of the Upper K4 (UK4) mining block at its flagship Lace diamond mine is on schedule for mining operations to start in the second half of the year – several months ahead of the original development schedule.

Underground core drilling of the UK4 block has delineated 2.6-million tons of high-grade kimberlite above the 370 m level – an increase of more than two-million tons over the original Lace geological model.

The final resource statement will require grade data from the bulk testing programme, which is currently scheduled to be completed by the end of the second quarter of this year.

The announcement follows the adoption of a revised underground development schedule and budget in 2014 that aimed to accelerate the ramp-up of commercial production from underground kimberlite mining by six months.

The main challenges to achieving this schedule and budget had been increasing input costs, the more than 25% devaluation of the rand against major currencies and a climate of industrial relations unrest in the South African mining industry strike.

Meanwhile, processing of K6 kimberlite has recovered from the production level drives and has resulted in the recovery of a 19.83 ct clear white gem diamond – the largest gem diamond thus far recovered from underground development.

The installation of the 400 t/h underground conveyor system, which will bring ore to surface for the life of the mine, is on schedule for commissioning ahead of the mining ramp-up. 

Key Contracts and Suppliers
None stated.

On Budget and on Time?
The mine’s ramp-up is expected to start six months ahead of the original schedule.

Contact Details for Project Information
DiamondCorp, tel +44 20 3151 0970, fax +44 20 3151 0971 or email info@diamondcorp.plc.uk.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest News

SKAO director-general Prof Jessica Dempsey
The SKA Observatory has a new head
2nd June 2026 By: Rebecca Campbell

Showroom

Columbus Stainless
Columbus Stainless

Columbus Stainless, based in Middelburg, Mpumalanga, is Africa’s only producer of stainless steel flat products. In addition, Columbus is the only...

VISIT SHOWROOM 
Kriel Occupational Health Centre
Kriel Occupational Health Centre

Occupational health services, mobile clinics, wellness campaigns, aviation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.062 1.473s - 147pq - 2rq
Subscribe Now