Kvanefjeld rare earths project, Greenland – update

12th February 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kvanefjeld rare earths project.

Location
The project is located in Kvanefjeld, in southern Greenland.

Project Owner/s
Greenland Minerals. Shenghe Resources has acquired a 12.5% interest in GMEL.

Project Description
The Kvanefjeld project is underpinned by the world’s largest code-compliant rare earths resource.

The outcomes of a feasibility study in 2016 demonstrated the potential of the project to be developed as a large-scale, low-cost producer of rare earths. The feasibility study envisaged the production of 30 000 t/y rare-earth oxide (REO) at a processing rate of three-million tonnes a year.

An optimised feasibility study was completed in May 2019, showing recovery improvements across the light and heavy rare-earth elements.

The increased recoveries will result in the production of 32 000 t/y REO at the processing rate of three-million tonnes a year adopted in the 2016 feasibility study.

The improved rare-earth recoveries have increased the projected output of commercially important rare earths to 4 260 t/y for neodymium oxide, 1 420 t/y for praseodymium oxide and 270 t/y for dysprosium oxide.

Average by-product output includes 451 t/y of uranium oxide, 6 060 t/y of zinc concentrate and 12 417 t/y of fluorspar. The increase in rare-earth recoveries is primarily owing to the design of a single-leach stage, which results in fewer solid/liquid separation stages. Each separation stage results in minor rare-earth losses. Kvanefjeld is well positioned to be a significant contributor to global rare-earth supply for an initial 37-year period, based on a 108-million-tonne ore reserve.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The 2016 feasibility study estimated the project’s net present value at $1.59-billion, at a 10% discount rate. The internal rate of return is 43.4% with a payback of five years.

Capital Expenditure
The projected capital cost for the Kvanefjeld rare earths project has been reduced by an estimated 40%, from $832-million to $505-million. This reduction resulted from optimisation studies covering all elements of the project, from the flowsheet to civil construction.

Planned Start/End Date
Not stated.

Latest Developments
Greenland’s government has extended the public consultation period for the Kvanefjeld rare earths project until June 1.

The extension will result in a 23-week consultation period, instead of the originally determined 12 weeks.

The company has said that the logistical constraints caused by the Covid-19 pandemic have created increased logistical challenges in holding public meetings and information forums, while government has also closed its borders from February 1 to February 28, imposing further limitations for specialist advisers and independent experts to participate in the consultation.

Further, municipal elections are also planned for April, which will affect the consultation process.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
GMEL, tel +61 8 9382 or fax +61 8 9382 2788.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ALBIS FLANGES (Pty) Ltd
ALBIS FLANGES (Pty) Ltd

ALBIS FLANGES — founded in 1965 — is a petro-chemical approved manufacturer of flanges and fittings in most grades of steel, listed with Sasol,...

VISIT SHOWROOM 
Sulzer Pumps (SA) (Pty) Ltd
Sulzer Pumps (SA) (Pty) Ltd

Sulzer South Africa, established in 1922, partners with critical industries like power, oil & gas, water, mining, and chemicals to boost...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.054 0.817s - 156pq - 2rq
Subscribe Now