Öksüt gold project, Turkey

28th August 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Öksüt gold project, Turkey.

Client
Centerra Gold.

Project Description
Based on a positive feasibility study, an estimated 26.1-million tonnes at an average grade of 1.4 g/t of measured and indicated resources has been converted to probable reserves using a gold price of $1 250/oz and a cutoff grade of 0.3 g/t gold.

The feasibility study envisions a conventional openpit and heap-leach operation. The heap-leach pad has been designed with an ultimate ore capacity of 40-million tonnes.

It is envisioned that a local contractor will conduct mining using a conventional truck-and-shovel fleet with small, selective, loading equipment and 36 t trucks.

The life-of-mine strip ratio is expected to be 2:1. Ore will be crushed to 38 mm through two stages of crushing and be placed on the heap-leach pad at a rate of 11 000 t/d. Life-of-mine gold recovery is expected to be 77%.

The project is expected to process 26.1-million tonnes of ore at an average grade of 1.4 g/t gold over eight years, producing 895 000 oz of gold at an average all-in sustaining cost of $490/oz.
Electrical power is expected to be supplied to the project by a dedicated 28 km power line tied into the local power grid.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value of $242-million, using an 8% discount rate, and a 42.5% internal rate of return. Payback on construction capital and preproduction expenditures is expected to be 2.5 years after production begins.

Value
Preproduction expenditure and construction capital are estimated at $221-million, including a $25-million contingency.

Duration
First gold production is targeted for early in the second quarter of 2017.

Latest Developments
The environmental-impact assessment (EIA) process continues on schedule, with formal EIA approval expected late in the third quarter or early in the fourth quarter of 2015.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Centerra Gold, tel + 416 204 1953 or fax +1 416 204 1954.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.044 0.907s - 127pq - 2rq
Subscribe Now