https://www.engineeringnews.co.za

Koeberg nuclear power station steam-generator replacement project, South Africa

25th March 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Koeberg nuclear power station steam-generator replacement project, Western Cape, South Africa.

Client
Eskom.

Project Description
The current steam generators in Unit 1 and Unit 2 at the Koeberg nuclear power station have been in operation since 1983/4 and 1984/5 respectively; as a result, Eskom plans to replace them.

This will involve the design, manufacture and installation of three steam generators in each of the two operating units, as well as the safety analyses and studies required for the replacement of the six steam generators.

The new generators will incorporate modern design features for easy maintenance and inspections, and improve heat-transfer efficiency, leading to the overall efficiency of the power station.

The installation of the generators will be conducted during the scheduled refuelling, inspections and maintenance outages of the two units at the power station.

Value
R4.3-billion.

Duration
Based on the lead times for the manufacture of six new steam generators, Eskom is planning for installation to take place in 2018.

Latest Developments
Areva has reported that 80% of the procurement associated with a contested contract to supply six replacement steam generators for the Koeberg nuclear power station has been completed and that 30% of the forgings have been delivered for manufacturing in China.

Eskom awarded the R4.3-billion Koeberg contract to Areva in September 2014, but Westinghouse Electric Company, which also bid for the contract, contested it and launched an expedited review application in the South Gauteng High Court.

The High Court found in favour of the State-owned utility, but following an appeal, the Supreme Court of Appeal (SCA) ruled in December last year that Eskom’s tender committee had acted unlawfully considering adjudication criteria not included in the original tender.

The SCA did not, however, interdict the contract from proceeding and instead referred the tender back to Eskom for reconsideration. Nevertheless, Eskom approached the Constitutional Court in January in a bid to have the SCA ruling overturned, a move that is being opposed by Westinghouse.

Eskom argues that it is prudent to replace the steam generators during scheduled shutdowns of the two Koeberg units in 2018 and that the contract should not be delayed. Westinghouse, however, argues that the replacement of the steam generators could be done during subsequent refuelling outages after 2018 without compromising safety.

Eskom CEO Brian Molefe has previously stressed that it is proceeding with the steam-generator replacement “not because there is going to be an outage, but because it’s the correct thing to do”. He notes that most other nuclear plants that operate 900 MW-series reactors, such as those deployed at Koeberg, have replaced their steam generators.

The steam generators are located within the reactor building alongside the reactor vessel, which heats water in a primary circuit to 320 °C, which is kept in a liquid state using a pressuriser. The heated water in the primary circuit enters the steam generator to produce steam in a secondary circuit, which is used to spin a turbine, connected to a generator to produce electricity.

Speaking during a recent media visit to Areva’s Chalon/Saint-Marcel plant, heavy equipment manufacturing line director Patrick Poret said that the contract was at an advanced stage.

He said the group was working in close association with Senpec, of Shanghai, China, where the Koeberg stream generators would be finally assembled ahead of delivery to South Africa.

“The procurement phase is already 80% completed and 30% of the forgings have already been delivered to Senpec for manufacturing,” Poret said, while pointing out various components being produced for the Koeberg contract during a factory tour.

Key Contracts and Suppliers
Group Five and Lesedi Nuclear Services (design, manufacture and replacement of refuelling water storage tanks); Areva (steam generators).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Eskom, tel +27 11 800 8111.
Group Five, tel +27 11 806 0111.
Lesedi Nuclear Services, tel + 27 21 525 1300 or fax +27 21 5251333.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

The Steel Tube Export Association of South Africa
Steel Tube Export Association of South Africa

The Steel Tube Export Association of South Africa was established to develop sustainable, internationally competitive carbon steel tube and pipe...

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.056 1.003s - 145pq - 2rq
Subscribe Now