Keliber lithium project, Finland
Name of the Project
Keliber lithium project.
Location
The project is located in Central Ostrobothnia, Finland.
Client
Keliber Oy.
Project Description
A definitive feasibility study has confirmed the project’s strong financial and technical feasibility. The project has total proven and probable reserves of 7.41-million tonnes grading 1.04% lithium oxide (Li2O) and total measured, indicated and inferred resources of ten-million tonnes grading 1.16% Li2O.
Based on current ore reserves, the project has a life-of-mine of 13 years. The project could be extended by seven years by acquiring spodumene concentrates from third parties after the mines are exhausted. There also exists significant exploration potential in the area, which creates the possibility of continuing the operation from the project’s reserves.
Conventional truck-and-shovel has been selected as the most suitable mining method for the openpit mining areas.
The main underground mining method com-prises bench-and-fill mining and is appropriate for this style of deposit, with the orebody being accessed from the decline. Mining will advance from the bottom upwards in 20-m-high mining lifts and backfill will be waste rock from the openpit and development drives.
The selected overall flowsheet comprises a conventional spodumene concentrator, conversion of alpha to beta spodumene in a rotary kiln and a soda pressure leach process to produce lithium carbonate.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of €295-million and an internal rate of return estimated at 24%, with a pretax payback of 5.5 years.
Value
The total project development capital cost estimate for the mines, concentrator and chemical plant is €255-million. The initial investment is €199-million, with the remaining €56-million to be invested later.
Duration
Not stated.
Latest Developments
None stated.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Keliber Oy tel +358 10 567 0600 or email info@keliber.fi.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation