https://www.engineeringnews.co.za

Karara needs more funding - Gindalbie

20th November 2013

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Iron-ore developer Gindalbie Metals has revised its production guidance for the Karara joint venture (JV) for the December quarter, and flagged the need for further investment.

Newly appointed MD Dale Harris noted on Wednesday that the commissioning and the ramp-up of the Karara concentrator had been slower than anticipated, adding that bottlenecks, particularly relating to the tailings system, had been identified and were currently restricting plant capacity.

Karara is expected to produce between 1.3-million and 1.5-million tonnes of magnetite during the three months to December, which is slightly below the previous guidance of between 1.5-million and 2-million tonnes.

Magnetite concentrate from the Karara JV would reach about 75% of the nameplate capacity by the end of March next year, following the completion of the tailings filters refurbishment programme and the construction of a temporary tailings facility.

Gindalbie continued to investigate options to further debottleneck the plant to achieve its nameplate capacity of eight-million tonnes a year, and operational improvement work would be ongoing as part of the ramp-up and optimsiation work through 2014.

Direct shipping ore production and shipments would also continue to supplement concentrate production during 2014, and would ensure that rail and port operations were running at Phase 1 design capacity.

Harris said that the JV vehicle would have a clear plan in place by the March quarter to achieve nameplate capacity, warning shareholders that it was likely that an additional capital investment would be required.

“We have continued strong support from our partner Ansteel and our clear priority for the next 12 months will be to resolve the bottlenecks with the plant, and to bed down and optimise the Stage 1 project,” he added.

In September, Ansteel provided $230-million in funding in an effort to boost the production ramp-up. The new funding was in addition to two previous cash injections by Ansteel earlier this year, consisting of $84-million and $30-million, respectively, to cover working capital requirements and to fund previous debt.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

The Beneficiation Academy
The Beneficiation Academy

The Beneficiation Academy is a certified training institution that follows all compliance legislation and is accredited with various Sector...

VISIT SHOWROOM 
The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.048 0.869s - 140pq - 2rq
Subscribe Now