Name of the Project
Kamoa-Kakula copper project.

Location
Kamoa-Kakula is a very large, near-surface, stratiform copper deposit with adjacent prospective exploration areas within the Central African Copperbelt, about 25 km west of Kolwezi, in the Democratic Republic of Congo (DRC).

Client
Ivanhoe Mines and Zijin Mining each hold an indirect 39.6% interest in the Kamoa-Kakula project, Crystal River Global holds an indirect 0.8% interest and the DRC government holds a direct 20% interest.

Project Description
The Kamoa-Kakula project has indicated mineral resources of 1.11-billion tonnes grading 2.78% copper and inferred resources of 261-million tonnes grading 1.94% copper.

Three potential development scenarios have been examined for the project:
1. The initial mine development scenario – the Kakula 2017 preliminary economic assessment (PEA) evaluates the development of a six-million-tonne-a-year underground mine and surface processing complex at the Kakula deposit (a discovery announced in early 2016), as the project’s first phase of development. For this option, the PEA envisages an average production rate of 246 000 t/y of copper for the first five years of operation and 385 000 t/y by Year 4.
2. The expanded, two-mine development scenario – the Kakula 2017 PEA also includes an option for an integrated, 12-million-tonne-a-year, two-stage development, beginning with initial production from the Kakula mine, followed by a separate underground mining operation at the nearby Kansoko mine, along with the construction of a direct-to-blister smelter, with a capacity of 690 000 t/y of copper concentrate. This scenario delivers average production of 370 000 t/y of copper in the first ten years of operation and production of 542 000 t/y by Year 9.
3. Kamoa 2017 prefeasibility study (PFS) – the PFS evaluates the development of the Kansoko mine as a standalone six-million-tonne-a-year underground mine and surface processing complex, which will be supplied with ore from the planned development of the Kansoko Sud and Kansoko Centrale areas of the Kamoa deposit, which were discovered in 2008. The PFS envisages average copper production at 178 000 t/y of copper for the first four years and 245 000 t/y by Year 7. Kamoa has an estimated mineral reserve of 125.1-million tonnes grading 3.81% copper.

Ivanhoe continues to explore options to increase Kamoa-Kakula production to 18-million tonnes a year and beyond. 

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The initial mine development scenario has an estimated after-tax net present value (NPV), at an 8% discount rate, of $4.2-billion and an internal rate of return (IRR) of 36.2%, with a payback of 3.1 years.

The expanded, two-mine development scenario has an estimated NPV, at an 8% discount rate, of $7.2-billion and an IRR of 33%, with a payback of 4.7 years.

The Kamoa 2017 PFS estimates an after-tax NPV, at an 8% discount rate, of $2.1-billion – an increase of 109%, compared with the after-tax NPV of $986-million projected in the March 2016 Kamoa PFS. The IRR is estimated at 24%, with a payback five years.

Value
The initial mine development scenario has an initial capital cost of $1.2-billion. For the expanded, two-mine development scenario, the PEA envisages $1.2-billion in initial capital costs. The Kamoa 2017 PFS estimates that the Kansoko mine will cost $1-billion to develop.

Duration
Not stated.

Latest Developments
Ivanhoe and Zijin are also exploring potential options to accelerate future production by building the Kakula and Kansoko mines concurrently, as well as expansions to 18-million tonnes a year and beyond as exploration progresses at Kamoa-Kakula and on Ivanhoe’s 100%-owned exploration licences in the Western Forelands area to the west of Kamoa-Kakula, where drilling has started.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Ivanhoe Mines (North America), tel +1 604 688 6630/+27 11 088 4300 (South Africa) or email info@ivanhoemines.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Trotech
Trotech

Design, Construction and Maintenance of Site Erected, Welded Bulk Storage Tanks for the Petrochemical, LNG, Ammonia and Sustainable fuel Sectors.

VISIT SHOWROOM 
Flanders Electrical SA
Flanders Electrical SA

FLANDERS Southern Africa provides integrated solutions for mining and industrial operations, covering field services, automation, electrification,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 0.856s - 157pq - 2rq
Subscribe Now