Kachi construction continues - Lake Resources
PERTH (miningweekly.com) – ASX-listed Lake Resources on Monday noted that construction of the demonstration plant at its Kachi lithium project, in Argentina, continued unabated, despite the dispute with partner Lilac Solutions.
Lake last week flagged the dispute with Lilac over the timeline for the Kachi pilot plant, with Lake holding that Lilac would have to reach its milestone earn-in by the end of September, while Lilac held firm that it had until November to reach these milestones to earn a 25% stake in the project.
The milestones included Lilac completing at least 1 000 hours of operation at the pilot plant and producing a lithium carbonate feed of at least 2 500 kg from on-site operations.
Lake on Monday told shareholders that construction of the facility to house the demonstration plant is now complete, and that dry commissioning started on September 14.
Subject to the completion of dry commissioning, Lilac expects to begin wet commissioning on September 22, and once this has been completed, the development partner will begin in-site processing of Kachi brines in the first week of October.
Lake said that while the test program is based on operating the demonstration plant for 1 000 hours it is anticipated that the first 2 000 litres of lithium concentrate produced from the demonstration plant will be sent for conversion into lithium carbonate once delivered.
Lake proposes that this final lithium product will then be qualified by a tier 1 battery maker to validate product specifications.
Offtake discussions for the lithium product continue to advance, the company added.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation