Kabanga nickel sulphide joint venture, Tanzania

22nd January 2010

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Kabanga nickel sulphide joint venture, Tanzania.

Project Description
The Kabanga nickel project is among the world's most attractive undeveloped nickel sulphide deposits, with a total estimated indicated mineral resource of 23,23-million tons, grading 2,64% nickel and a total estimated inferred resource of 28,5-million tons grading 2,7% nickel. The new resource estimate represents a significant increase from the project's initial 2005 estimate (inferred) of 26,4-million tons at 2,6% nickel.

The proposed facility under study is an underground mine, milling and concentrator facility located at the Kabanga site. The concentrate is proposed to be transported to the Port of Dar es Salaam by road and existing rail infrastructure where it will be shipped to Xstrata's Sudbury smelter and other custom feed customers.

Duration
A full feasibility study was expected to be completed by the end of 2009.

Client
The Kabanga project is a 50:50 joint venture between Xstrata Nickel and Barrick Gold Corporation.

Key Contracts and Suppliers
None stated.

Latest developments
None stated.

Contact details for project information
Barrick Gold Corporation, tel +1 416 861-9911 or fax +1 416 861 2492.
Xstrata Nickel, tel +1 416 775 1500.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Airshrink - CiP
Airshrink - CiP

At Airshrink - CiP, we surpass customer expectations with innovative MV and LV cable accessories, including heat shrink joints, terminations,...

VISIT SHOWROOM 
Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.078 0.892s - 148pq - 2rq
Subscribe Now