Jansen potash project, Canada – update

25th June 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Jansen potash project.

Location
About 140 km east of Saskatoon, in Saskatchewan, in Canada.

Project Owner/s
Multinational mining company BHP.

Project Description
The Jansen potash project has an estimated measured resource of 5.17-billion tonnes and an inferred resource of 1.27-billion, both grading 25.7% potassium oxide, 7.1% insolubles and 0.07% magnesium oxide.

The project is being designed to produce about eight-million tonnes a year of agricultural-grade potash in three phases. The project has an estimated 70-year life-of-mine.

The current scope of work involves the completion of the excavation and lining of the production and service shafts, as well as the continuance of the installation of essential surface infrastructure and utilities.

Capital Expenditure
The project is expected to cost up to $5.7-billion in its first phase.

Planned Start/End Date
The Jansen Stage 1 potash project will be presented to the BHP board for a final investment decision in the second half of 2021.

The company previously planned to present the project to its board in February 2021, but delays pertaining to the completion of shafts have resulted in a later date.

The delays are a result of initial challenges regarding the placement of the shaft lining, which have since been rectified. The group’s Covid-19 response plan has also impacted on work.

Latest Developments
BHP expects to present its board with a decision on whether to proceed with its Jansen potash project in a few months, after choosing between two port options.

"We are considering two options in terms of the port. One is a commercial option at the Port of Vancouver; one is a greenfield option," BHP Minerals America president Ragnar Udd has told investors.

BHP has said that a decision will be made mid-2021, although it might be "a slightly wider range”, CEO Mike Henry has said

Key Contracts, Suppliers and Consultants
DMC Mining Services (development of two new mine shafts) and SNC-Lavalin (feasibility study for Jansen Phase 1, as well as engineering, procurement and construction management services for Phase 1).

Contact Details for Project Information
BHP, tel +61 3 9609 3333.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.056 0.098s - 149pq - 2rq
Subscribe Now