Project Description
The Jansen potash project has an estimated measured resource of 5.17-billion tonnes and an inferred resource of 1.27-billion, both grading 25.7% potassium oxide, 7.1% insolubles and 0.07% magnesium oxide.
The project is being designed to produce about eight-million tonnes a year of agricultural-grade potash in three phases. The project has an estimated 70-year life-of-mine.
The current scope of work involves the completion of the excavation and lining of the production and service shafts, as well as the continuance of the installation of essential surface infrastructure and utilities.
Capital Expenditure
Not stated.
Planned Start/End Date
The Jansen Stage 1 potash project will be presented to the BHP board for a final investment decision in the second half of 2021.
The company previously planned to present the project to its board in February 2021, but delays pertaining to the completion of shafts have resulted in a later date.
The delays are a result of initial challenges regarding the placement of the shaft lining, which have since been rectified. The group’s Covid-19 response plan has also impacted on work.
Latest Developments
BHP Group is in talks with Nutrien about a potential partnership in the Jansen potash project as it progresses towards a final decision on the project.
The companies are discussing multiple options, including Nutrien’s becoming the operator and selling the potash through its existing channels or the company taking a stake in the Jansen mine, according to people familiar with the matter; however, there is no guarantee that the talks will lead to a deal.
BHP has struggled with the Jansen project for years. Despite spending about $4.5-billion and digging two 1 000 m deep shafts, the company has yet to approve its construction and has faced shareholder opposition, including from Elliott Investment Management. BHP’s board is set to make a final decision in the coming months.
Key Contracts, Suppliers and Consultants
DMC Mining Services (development of two new mine shafts) and SNC-Lavalin (feasibility study for Jansen Phase 1, as well as engineering, procurement and construction management services for Phase 1).
Contact Details for Project Information
BHP, tel +61 3 9609 3333.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation