Hunter Power project, Australia

Name of the Project
Hunter power project.
Location
At the old Kurri Kurri aluminium smelter site in the Hunter region of New South Wales, in Australia.
Project Owner/s
Snowy Hydro.
Project Description
The proposed project will fill the void in electricity demand and ensure security of supply following the retirement of the Liddell power station, in Muswellbrook.
The business case requires the construction of a 660 MW plant using two high-efficiency, hydrogen-ready industrial units.
The open-cycle gas turbines will initially be capable of running on up to 10% hydrogen and, with some minor additional investment, they will be capable of up to 30%, subject to fuel logistics.
The project includes the construction and operation of a power station and electrical switchyard, as well as other associated fuel gas and diesel supply assets.
Potential Job Creation
The project is expected to support up to 600 direct jobs at peak construction and 1 200 indirect jobs across New South Wales.
Capital Expenditure
The New South Wales government is providing up to A$600-million in equity to support the construction of the project.
Planned Start/End Date
The power plant will come online in 2023.
Latest Developments
The New South Wales government has awarded Snowy Hydro environmental approval for the construction of the Hunter power project.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
Snowy Hydro, tel +61 2 6453 2888 or email info@snowyhydro.com.au.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation