Hummingbird to reach first gold pour this quarter at Guinea mine

2nd May 2023

By: Tasneem Bulbulia

Deputy Editor Online

     

Font size: - +

Aim-listed Hummingbird Resources says the Kouroussa gold mine processing plant has reached the practical completion stage and has entered the commissioning phase towards achieving first gold pour later this quarter.

The Kouroussa gold mine, in Guinea, is a high-grade, over 4 g/t openpit operation, and is the company’s second operating gold asset in West Africa.

Practical completion on priority systems at the Kouroussa processing plant has now been achieved, allowing the commissioning phase to begin.

Pre-operational and cold commissioning is currently under way and, once completed, will move to the hot commissioning phase, followed by the first gold pour.

Soutex, Kouroussa’s engineering contractor, along with specialist Hummingbird commissioning personnel, are working together on site to coordinate the commissioning phase.

Sufficient ore feed tonnes are on the run-of-mine (RoM) pad for commissioning, with mining activities accelerating to provide increased ore feed tonnes on the RoM pad for first gold pour, followed by nameplate production.

Hydrotesting has been completed on the pre-leach, carbon in leach, raw water and reagent tanks, with mechanical equipment pre-operational testing also in progress.

Cold commissioning has started on priority water and air services systems.

Original-equipment manufacturer vendors are on site for dry and wet plant equipment commissioning.

“Kouroussa is on track to pour first gold within the current quarter, and the start of commissioning of the processing plant is a significant step forward in achieving this objective. As we begin the commissioning phase to bring Kouroussa online, we remain heavily focussed on safety at this busy time.

“Additionally, operational readiness and the transition to daily operations is a key part of this phase as we look not just to first gold, but to ramping up production to nameplate capacity, moving the company to being a 200 000-oz-plus, multi-asset, multi-jurisdiction gold producer,” says CEO Dan Betts

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.052 0.904s - 140pq - 2rq
Subscribe Now