Houndé gold project, Burkina Faso

3rd November 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Houndé gold project.

Location
The project is located within the Birimian greenstone belt in Burkina Faso, just south of Semafo’s Mana mine and about 250 km south-west of the capital city, Ouagadougou, and benefits from excellent existing infrastructure.

Client
Houndé Gold Operation, Endeavour Mining’s Burkina Faso operating subsidiary.

Project Description
With its robust grade and low cash costs, Houndé ranks among West Africa’s highest-quality gold development projects.

Once in full production, Houndé is expected to become Endeavour’s flagship low-cost operation, with a life-of-mine of more than ten years.

Endeavour Mining expects to produce an average of 190 000 oz/y at an all-in sustaining cost (AISC) of $709/oz over the life-of-mine. Over its first four years, Houndé’s average production is expected to be 235 000 oz/y at an AISC of $610/oz.

A 34% increase in the estimated mineral reserve has resulted in greater output expectations and a longer mine life.

The project has proven and probable reserves of 30.6-million tonnes, with an average grade of 2.1 g/t gold.

The updated mine plan defines a large-scale openpit mine that provides 29.7-million tonnes of ore at 2.15 g/t of gold and 251-million tonnes of waste for a strip ratio of 8.4:1.

The enhanced production, relative to the November 2013 feasibility study is a result of the exploration additions from 2014 and an optimisation of the mine plan to access high-grade and shallow gold-mineralisation during the initial years of the mine life.

The processing plant consists of a three-million-tonne-a-year gravity circuit/carbon-in-leach (CIL) plant with a semiautogenous (SAG) ball crushing comminution circuit.

Additional infrastructure includes the construction of the 38-km-long, 91 kV overhead power line.

Exploration potential
The Houndé exploration tenement covers more than 1 075 km2 within the highly prospective Birimian greenstone belt. Following a two-year period of no drilling, exploration activities will resume in 2017, with a $5-million programme totalling an estimated 45 000 m.

The focus will be on delineating high-grade targets, such as Bouere and Kari Pump, in addition to performing reconnaissance drilling.

Openpit prestrip mining at the main Vindaloo openpit, adjacent to the processing facility, also started in late 2016.

The enlarged reserve will result in total gold production of about 1.9-million ounces over a ten-year mine life, compared with the originally estimated 1.4-million ounces over an eight-year mine life.

Potential Job Creation
More than 2 000 personnel, including contractors, are on site, more than 94% of whom are Burkinabe.

Net Present Value/Internal Rate of Return
The internal rate of return has increased from the previously estimated 22.4% to 32% at a gold price of $1 250/oz.

The project’s after-tax net present value has been estimated at $359-million at the same gold price.

Value
The updated capital cost is estimated at $328-million, including contingency, working capital and import duties.

This represents a 3.2% increase over the $315-million estimate in the November 2013 feasibility study.

Duration
The Houndé mine began processing ore ahead of schedule on September 25 and achieved its first gold pour on October 18.

Latest Developments
The development of the Houndé project has been completed, with commercial production declared more than two months ahead of schedule, $15-million below its initial capital budget and at full nameplate capacity, with all key metrics ahead of the assumptions set out in the feasibility study.

The current stockpile totals 571 000 t at 2.6 g/t containing 47 000 oz, inclusive of 130 000 t at more than 5 g/t.

Resettlement compensation for communities living near the high-grade Bouere and Dohoun satellite deposits has started, with mining activities scheduled to begin in late 2018.

Meanwhile, exploration drilling, which resumed in early 2017 following a two-year period of inactivity, has confirmed the occurrence of high-grade mineralisation at the nearby Kari Pump and other targets, with the initial results expected to be published in the coming weeks.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
The project has been completed ahead of schedule and below budget.

Contact Details for Project Information
Endeavour Mining, tel +44 203 640 8665 or email info@endeavourmining.com.
 
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest News

SKAO director-general Prof Jessica Dempsey
The SKA Observatory has a new head
2nd June 2026 By: Rebecca Campbell

Showroom

Columbus Stainless
Columbus Stainless

Columbus Stainless, based in Middelburg, Mpumalanga, is Africa’s only producer of stainless steel flat products. In addition, Columbus is the only...

VISIT SHOWROOM 
Kriel Occupational Health Centre
Kriel Occupational Health Centre

Occupational health services, mobile clinics, wellness campaigns, aviation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.155 1.071s - 147pq - 2rq
Subscribe Now