Group Five says Ghanaian power project delayed

6th November 2018

By: Reuters

  

Font size: - +

South African engineering firm Group Five said on Tuesday that construction on its Ghanaian Kpone power plant had been delayed once again due to fuel contamination.

The power plant, whose construction begun in 2015 and was due to be completed in 2017, had previously been delayed due to the late arrival of materials and difficulties with some sub-contractors.

"The provision of fuel is the client's responsibility. The completion and hand over date will therefore be delayed, as it is dependent on the resolution of the fuel contamination," Group Five said in a statement.

Group Five is currently disputing a claim of $62.7-million made by a customer, Cenpower Generation Company Ltd, for project delays.

The company incurred R1.3-billion ($91.57-million) in losses for the financial year ended June 2018, the bulk of which were owed to the Kpone project.

The company is going through a restructuring in which it has closed multiple non-profitable businesses locally and cut 602 permanent staff in the 2018 financial year.

South African construction companies have borne the brunt of stagnant economic growth that has hobbled public infrastructure spending in recent years.

Shares were down 0.86 percent to 1.15 rand by 1017 GMT after falling as much as 13 percent earlier.

Edited by Reuters

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Iritron
Iritron

Iritron delivers advanced automation, control, and optimisation solutions to the Mining, Minerals & Metals, Consumer Package Goods and...

VISIT SHOWROOM 
Airshrink - CiP
Airshrink - CiP

At Airshrink - CiP, we surpass customer expectations with innovative MV and LV cable accessories, including heat shrink joints, terminations,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.048 0.878s - 135pq - 2rq
Subscribe Now