Gindalbie sets record shipments from Karara
PERTH (miningweekly.com) – Iron-ore miner Gindalbie Metals has shipped 2.4-million tonnes of ore during the three months to December, with total shipments through the Karara export terminal hitting a record annualised rate of 9.47-million tonnes a year during the quarter.
The miner said on Friday that the 39 shipments during the quarter consisted of 0.9-million tonnes of magnetite concentrate and 1.5-million tonnes of hematite direct shipping ore (DSO).
Some 829 000 t of hematite concentrate was produced at Karara during the quarter, along with 756 000 t of hematite DSO. Both magnetite and hematite production were up on the previous quarter, as the Karara project continued its ramp-up.
For the six months to June, Gindalbie was expecting to produce between 2.4-million and 2.7-million tonnes of hematite concentrate and between 1.6-million and 1.8-million tonnes of hematite DSO.
Meanwhile, the miner has assured shareholders that a technical review of the Karara operation was on track for completion during the March quarter. The review would outline a clear plan and timetable to achieve nameplate capacity.
The magnetite concentrator was expected to reach 75% of nameplate capacity by the end of March this year, following the completion of the tailings filter refurbishment programme and the construction of a temporary tailings facility.
Gindalbie has previously warned that the project would require additional capital investment to reach its capacity goals by March.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation