Fruta del Norte gold project, Ecuador
Name of the Project
Fruta del Norte (FDN) gold project.
Location
Ecuador.
Client
Lundin Gold.
Project Description
FDN has mineral reserves totalling 15.5-million tonnes at 9.67 g/t of gold and 12.7 g/t of silver.
A feasibility study on the project envisions a mine with production estimated at 4.4-million ounces of gold and 5.2-million ounces of silver over an initial 13-year mine life, and an average gold recovery of 91.7% and average silver recovery of 81.5%.
Average gold production is estimated at 340 000 oz/y at an average life-of-mine (LoM) total cash cost of 553/oz and aN LoM all-in sustaining cash cost of $623/oz, placing FDN in the lowest cash cost quartile globally.
Twin declines will be built using a spiral to gain depth to maximise the distance from the surface, so that a vertical distance of about 155 m below the Machinaza river can be obtained.
The mine ramp will be located centrally and will be offset by about 50 m from the main workings to the east of the deposit.
The ramp configuration will enable haulage trucks to achieve higher-average haul speeds and maintain safety standards.
The ramp will be developed at an estimated 15% gradient.
FDN ore will be processed using a gravity, flotation and leaching (GFL) flowsheet.
The GFL process is best suited to recovery of FDN gold because of the manner in which the gold is contained in the ore.
Following a conventional semiautogenous/ball mill grinding circuit, the gravity circuit will recover the coarse free gold, and small amounts of fine free gold and gold contained in sulphides.
The flotation circuit can recover the gold associated with sulphides (pyrite). The flotation tailings will be treated in a carbon-in-leach circuit that will recover the fine gold.
The final tailings will be either filtered and sent to the mine as paste backfill or deposited in a conventional tailings storage facility.
Over the life of the mine, about 70% of the gold will be produced in concentrate and the remainder in doré.
Silver production is estimated at 82% in concentrate and 18% in doré.
The concentrate is expected to have an average gold grade of 149.3 g/t and will be a marketable concentrate, with no significant penalty elements.
The doré is expected to contain more than 98% of precious metals.
The precious metal portion is expected to contain about 60% of gold and 40% of silver.
Jobs to be Created
Not stated.
Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 5% discount rate, of 1.28-billion and an internal rate of return of 23.8%, with a payback of 3.7 years.
Value
The cost of the project, including contingency, is estimated at $669-million.
Duration
Construction is expected to start in mid-2017, with first gold production expected in the first quarter of 2020 and the first full year of production in 2021.
Latest Developments
The government of Ecuador has approved the environmental-impact statement (EIS) for Lundin’s Fruta del Norte project.
The next and final step in the environmental approval process, paving the way for proceeding with the development of the project, is the granting of the environmental licence, a procedural process expected to be completed over the next few weeks.
“The approval of the EIS demonstrates the commitment of the government of Ecuador to move Fruta del Norte towards construction and eventual production,” commented Lundin Gold president and CEO Ron Hochstein.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Lundin Gold, tel +1 604 689 7842, fax +1 604 689 4250 or email info@lundingold.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation