Focus on ‘core underlying issues’ to tackle load-shedding crisis – EIUG

A power line tower

Photo by Creamer Media

1st July 2022

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

Ending the current restrictions to the addition of new generation capacity and addressing Eskom’s deteriorating generation performance are key to arresting intensifying load-shedding, the Energy Intensive Users Group (EUIG) asserts.

CEO Fanele Mondi said in a statement the recent illegal industrial action had escalated the crisis but stressed that the “core underlying issues” remained Eskom’s poor generation performance and the prevailing restrictions on the addition of new generation capacity.

“The EIUG believes strongly that our focus should be on fundamental issues, such as creating time for Eskom to undertake maintenance, streamlining Eskom’s procurement processes, dedicating funds for maintenance, executing effective maintenance practices, enhancing demand-side management, adding additional capacity through public and private generation projects, and further structural reforms,” Mondi said in a statement released as Eskom was implementing Stage 4 to Stage 6 load-shedding.

“To end load-shedding, generation performance needs to be improved while concurrently adding generation capacity to the grid as soon as possible,” Mondi said.

Eskom has indicated that up to 6 000 MW of new generation capacity is required to create the space it requires to maintain its aging and neglected coal fleet.

The utility has initiated roundtable discussions with energy experts to discuss ways to end load-shedding, as well as to create an electricity supply industry that is able to provide stable and affordable electricity, while dramatically reducing emissions.

CEO André de Ruyter reported on July 1 that supply- and demand-side options for ending load-shedding were discussed during the first roundtable, which met on June 24.

He said that these options were currently under consideration, but that some would require “policy interventions”.

“We have been engaging with our shareholder and we will leave that to the policy side to decide on, but we have certainly provided our input into opportunities for us to bring a rapid conclusion to load-shedding through interventions on both the supply and the demand side.”

The utility has also identified a second parcel of grid-ready land in Mpumalanga that it intends to offer, in the form of long-term lease agreements, to those private entities willing to invest in new distributed generation to take advantage of a dispensation allowing plants below 100 MW to proceed without a licence.

“We intend to approach the market by August,” De Ruyter confirmed.

Earlier, Eskom announced that 18 companies had been selected following its first land-release bidding process.

The projects could add a total of 1 800 MW of generation capacity once connected and cover about 4 000 ha out of the total 36 000 ha available under the programme.

 

 

Edited by Creamer Media Reporter

Comments

Showroom

SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.108 0.161s - 163pq - 4rq
Subscribe Now