First Cobalt refinery project, Canada – update
Name of the Project
First Cobalt refinery project.
Location
Ontario, Canada.
Project Owner/s
First Cobalt Corp.
First Cobalt and Glencore AG agreed to a partnership framework in July 2019, providing for a nondilutive, fully funded, phased approach to recommission the refinery. Subject to certain conditions, including the completion of a positive feasibility study and agreement upon commercial terms, the framework agreement envisages that First Cobalt will treat cobalt feed material supplied from Glencore’s Democratic Republic of Congo operations for an initial term of up to four-and-a-half years on a tolling basis. Glencore will provide up to 100% of the capital required to recommission and expand the facility.
Project Description
The First Cobalt refinery is a hydrometallurgical cobalt refinery with a nominal throughput of 12 t/d, producing a cobalt carbonate product along with nickel carbonate and silver precipitate. The facility incorporates two settling ponds and an autoclave pond, as well as a large warehouse building that once housed a conventional mill.
The independent feasibility study conducted on the proposed permitted cobalt refinery envisages the expansion of the existing facility to 55 t/d and adapting it to be North America’s first producer of cobalt sulphate, an essential component in the manufacturing of batteries for electric vehicles (EVs).
The proposed new layout adds two new simple engineered structures to the main complex – one for tailings belt filters and the other for crystallisation and product bagging. A new external building is also contemplated to house an expanded solvent-extraction circuit and sodium management infrastructure.
Other changes to the site layout include additional tankage for reagent storage in the tank farm area and improvements to the ring road around the refinery to accommodate transport trucks.
The objective is to produce about 25 000 t/y of cobalt sulphate for the EV market.
Cobalt hydroxide feed is estimated at 18 369 t and cobalt production at 5 096 t.
In tandem with the feasibility study, First Cobalt has completed a prefeasibility- (PFS-) level assessment of an early restart of the refinery using existing permits and equipment to operate at 12 t/d. The resulting prefeasibility report was intended as a benchmark from which various restart scenarios could be assessed.
Key differences in the 12 t/d demonstration plant scenario, compared with the 55 t/d feasibility study, include the treatment of a different cobalt alloy feedstock, with higher reagent requirements that significantly increases operating costs, and continuing to use the current tailings management facility rather than the dry-stack tailings design included in the 55 t/d feasibility study.
Using the PFS as a benchmark, three scoping studies are under way to assess alternate early commissioning scenarios.
In the first scenario, the refinery throughput would be reduced below 12 t/d to reduce the capital costs of a restart while enabling the refinery to operate as a demonstration plant to qualify cobalt sulphate product according to EV manufacturer specifications.
Under a second and third scenario, the refinery would initially be restarted at 12 t/d as a demonstration plant and would, over time, be retrofitted with a nominal 43 t/d hydroxide circuit and then either be combined into one circuit or left as two circuits capable of receiving different feedstocks. Results from the PFS and the three scoping studies will guide the company’s restart strategy.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
Based on a cobalt price of $25/lb, the project has pretax net present value, at an 8% discount rate, of $192-million and a pretax internal rate of return of 64%, with a payback period of only 1.8 years.
Capital Expenditure
The project has an initial capital estimate of $56-million; however, First Cobalt is evaluating opportunities to improve economics.
Planned Start/End Date
The project is expected to come on line in the final quarter of 2021.
Latest Developments
First Cobalt has signed an offtake agreement with cobalt trader Stratton Metal Resources for the sale of future cobalt sulphate production from the First Cobalt refinery.
First Cobalt will have the option to sell up to 100% of its yearly production to Stratton Metals once its refinery is in production. Quantities will be determined by First Cobalt in advance of each calendar year and are subject to a minimum yearly quantity.
The ability to elect the yearly quantity sold to Stratton Metals will provide the company with time and flexibility to advance offtake and battery recycling discussions with potential original-equipment manufacturer partners.
The five-year offtake contract matches the expected term of a project debt facility currently being negotiated, as well as long-term arrangements for refinery feedstock. In January, First Cobalt concluded five-year cobalt hydroxide feed purchase arrangements with Glencore and IXM.
Refinery commissioning remains on schedule for October 2022.
Key Contracts and Suppliers
Ausenco Engineering Canada (independent feasibility study); Knight Piésold (geotechnical drilling); and Story Environmental (permit to take water).
Contact Details for Project Information
First Cobalt investor relations, tel+1416900 3891 or email info@firstcobalt.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation













