First Cobalt targets Canada plant restart within 2 years – CEO
SHANGHAI – First Cobalt aims to restart an idled cobalt refinery in Canada within two years and is in talks to supply the battery-grade product to four leading automakers, CEO Trent Mell said on Wednesday.
The Toronto-based company is planning a $30-million revamp of the plant, located in the appropriately named town of Cobalt, Ontario, which has been shut down since 2015.
The restart would provide US end-users of cobalt, a key ingredient in rechargeable batteries for electric vehicles (EVs), with a refining base nearer to home than China, where most of the world's cobalt refining capacity is located.
"If we can short-circuit the logistics, it provides a ready source of sulphate for the US supply chain," Mell told Reuters in an interview in Shanghai.
The refinery was commissioned in 1996, when it ran on locally sourced cobalt and produced cobalt carbonate used in animal feed – long before the EV revolution took hold.
First Cobalt, which plans to produce cobalt sulphate from the plant, has already carried out a test using cobalt hydroxide from the Democratic Republic of Congo, where most of the world's mined cobalt supply comes from, as feedstock.
"The results that came out last week are indeed that it works," said Mell, who is targeting just over 2 000 t of cobalt sulphate per year, or enough to supply one EV maker.
The four automakers in talks with the company are "big global players" who make cars in the US, he said without disclosing their identities.
"A couple of them are already producing EVs and a couple of them are not yet there" but looking to the future, he added.
Cobalt prices are currently around $33 000/t, barely one-third of the peak of over $95 000/t in March 2018.
"It's not always easy to have all your material delivered to the big Chinese refiners when the price is coming down," Mell said, noting that US imports of cobalt from China are currently subject to a 10% import tariff.
Mell is giving himself six months to select a cobalt hydroxide feedstock, after which he said there will be an 18- to 24-month process before the restart.
"Six months to me is a long time, " he said. "If we can compress that, I'd love to think we'll be in production in two years."
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation