https://www.engineeringnews.co.za

Far West Gold Recoveries operation, South Africa – update

Image of Far West Gold Recoveries plant

Photo by DRDGOLD

7th February 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Far West Gold Recoveries (FWGR) operation.

Location
Gauteng, South Africa.

Project Owner/s
DRDGOLD’s acquisition of Sibanye-Stillwater’s West Rand Tailings Retreatment Project assets was finalised on July 31, 2018. Following the successful implementation of the transaction between the two companies, Sibanye owned 38.05% of the issued share capital of DRDGOLD.

Under the terms of the transaction, entered into in November 2017, Sibanye agreed to exchange selected surface-gold processing assets and tailings storage facilities (TSFs) for shares in DRDGOLD.

Sibanye-Stillwater also had an option to subscribe for further shares in DRDGOLD within 24 months at a 10% discount. In January 2020, Sibanye exercised this option, obtaining a 50.1% controlling interest in DRDGOLD.

Project Description
FWGR is a surface gold retreatment operation, which treats old slime dams in the West Rand goldfields. The operation is being rolled out in a phased approach.

Phase 1 included early-stage production, involving upgrading the Driefontein 2 plant (DP2) to process tailings from the Driefontein 5 dump at between 400 000 t and 600 000 t a month, and depositing the residue on the Driefontein 4 tailings dam, which was upgraded to a cyclone deposition dam to cater for the higher throughput.

Phase 2 envisages the construction of a high-volume central processing plant capable of processing between 1.2-million and 2.4-million tonnes a month, the continued use of DP2 at an increased 600 000 t a month, and the development of a new 800-million-tonne regional TSF (RTSF) capable of receiving up to three-million tonnes a month. 

In this phase, reclamation will initially be from the Driefontein 3, Libanon and Kloof 1 dumps, and then from the Ventersdorp North and South dumps. The scale of the infrastructure established in this phase will allow for the reclamation from other sources in the region. The objective is to clean up the regional landscape by reprocessing tailings that are currently on dolomite, and redeposit the reclaimed material onto a properly designed and managed megadam, thereby reversing the potential pollution of underground water in the region.

As an alternative to Phase 2, or should Phase 2 be delayed, Phase 1 can be extended by extending deposition onto the Driefontein 4 tailings dam, owing to the good cyclone splits being achieved at the tailings dam. Envisaged is the treatment of the remaining tonnes from Driefontein 5 and then processing material from Driefontein 3.

Potential Job Creation
Since its inception, FWGR has secured employment for more than 150 employees and is committed to its environmental, social and governance mandate, as well as social upliftment programmes, in the far West Rand area of operations. With the implementation of Phase 2 and the extended life-of-mine (LoM), more opportunities are expected to result from DRDGOLD’s value creation activities.

Capital Expenditure
DRDGOLD invested R330-million of capital in Phase 1.

DRDGOLD reported in August 2024 that it anticipated capital investment of about R7-billion at FWGR over the next five years.

Planned Start/End Date
Phase 1 commercial production started within eight months of the acquisition, on April 1, 2019, and made its maiden full 12-month contribution to DRDGOLD’s financial results in the 2020 financial year.

Beneficial occupation of the RTSF is targeted for the second half of the 2027 calendar year.

Monthly throughput capacity of 1.2-million tonnes at the DP2 is planned for the second half of the 2027 calendar year. This could potentially add 25 years to FWGR's LoM.

Latest Developments
DRDGOLD noted in its results for the six months ended December 31, 2024, published in February 2025, that significant progress had been made in the construction of the RTSF, with more than more than two-million cubic metres of ground moved in respect of work on the starter wall, the levelling of the basin and return water dams. 

It further noted that civil work on the upgrading of the DP2 – to increase its throughput capacity to 1.2-million tonnes a month – was also progressing well and would continue to be a key focus area in the months to come.

Key contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
R&A Strategic Communications on behalf of DRDGOLD, Jane Kamau, tel +27 11 880 3924 or email jane@rasc.co.za.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Axiom Hydraulics
Axiom Hydraulics

Axiom Hydraulics is a trusted leader in South Africa’s hydraulic industry, delivering world-class components, systems, and engineering expertise...

VISIT SHOWROOM 
MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.06 1.184s - 165pq - 2rq
Subscribe Now