Eskom’s China loan facility not in jeopardy – Public Enterprises
The Department of Public Enterprises says that power utility Eskom’s multi-billion rand loan facility with the China Development Bank is not in jeopardy, despite concerns sparked by a delay in the release of a R7-billion tranche of funds last month.
The bank was meant to release the funds - part of a larger R35-billion facility - in April. Absa Capital had to provide assistance after the loan failed to come through in time.
A Treasury report signed by Finance Minister Tito Mboweni in April said the delay in releasing the funds was due to Chinese exchange control requirements.
According to Chris Yelland, investigative editor at EE Publishers, however, the delay may have in fact resulted from "Chinese concerns as to whether Kusile would in fact proceed to completion, which was something Eskom and DPE had said they were still investigating."
Eskom spokesperson Adrian Lackay told Fin24 via a statement on Friday morning that the loan agreement with the CDB remained a binding agreement. It was concluded in July 2018 during the Brics summit in Johannesburg.
"I am advised that neither the loan facility nor the R7-billion drawdown that Eskom wants to access at this time, are in jeopardy," said Lackay.
He said one condition of the CDB loan agreement is that it be used only for capital expenditure, under government guarantee, and not for operational expenses.
"It must be emphasised, for the sake of clarity, that this, or any other loan, is in no way connected to the issue of equity in any of our state-owned enterprises," Lackay said.
Lackay added that the South African government – through National Treasury, the Department of Public Enterprises and Eskom – were working through the administrative aspects of the loan facility, including approvals for transfer from the CDB and receipt by Eskom.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation