https://www.engineeringnews.co.za

Eskom warns of Stage 2 load-shedding at peak hours this week

Electricity pylons

Photo by Creamer Media

22nd August 2022

By: News24Wire

  

Font size: - +

After three days without load shedding, Eskom warned that Stage 2 load-shedding might be implemented at short notice from 16:00 to 24:00, the peak evening hours, over the course of the week. 

This is due to power station breakdowns and delays in returning some generating units to service.

The breakdown of two generation units at Arnot, one each at Camden and Lethabo power stations during the past 24 hours and the delay in returning a generating unit to service each at Kendal, Komati and two units at Tutuka power stations have put a severe strain on the power generation system.

Over the weekend, Eskom returned to service two generating units at Kendal Power Station and a unit each at Hendrina, Kusile and Tutuka power stations.

Some 4 872MW in power output is out due to planned maintenance, while another 13 983MW of capacity is unavailable due to breakdowns.

Edited by News24Wire

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 
Columbus Stainless
Columbus Stainless

Columbus Stainless, based in Middelburg, Mpumalanga, is Africa’s only producer of stainless steel flat products. In addition, Columbus is the only...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.057 1.13s - 163pq - 2rq
Subscribe Now