Eskom implements continuous Stage 2 load-shedding until Friday after more breakdowns
Eskom will implement continuous Stage 2 load-shedding from Wednesday morning until 05:00 on Friday.
This follows two nights of Stage 2 due to numerous breakdowns at power stations. Eskom had initially anticipated carrying on with overnight load-shedding for the rest of the week, but more units have now failed.
"The extension of load-shedding is caused by the failure of additional units and the continued shortage of generation capacity due to delays in returning to service three generating units at Camden power station and two generating units at Tutuka power station," the power utility said early on Wednesday morning.
"Overnight a generation unit each at Medupi, Matla, Kendal and Komati power stations failed while 240 MW of power imports from Mozambique was interrupted, exacerbating the supply constraints."
Eskom said that 5 379 MW of capacity is not available due to planned maintenance, while another 14 827 MW is not available due to unplanned breakdowns.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation