Equinox marks first gold pour at Greenstone mine

24th May 2024

By: Creamer Media Reporter

     

Font size: - +

Canadian miner Equinox Gold has successfully poured its first gold at the newly built Greenstone mine, in Ontario.

The inaugural gold pour occurred on schedule, with the recovery circuit yielding 1 800 oz of gold.

Equinox reports that all equipment functioned as expected during the process.

“This first gold pour represents another key step towards achieving commercial production at the Greenstone mine. We look forward to ramping up to commercial production in the third quarter of this year,” says president and CEO Greg Smith.

The Greenstone mine is poised to become Equinox’s flagship asset and its largest, most cost-effective producer. At full capacity, the mine is projected to generate approximately 400 000 oz/y of gold over the initial five years of operation. Furthermore, it is expected to maintain an average production rate of 360 000 oz/y of gold throughout its initial 14-year mine life, positioning Greenstone as one of Canada's premier gold mines in terms of both scale and longevity.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.055 1.311s - 140pq - 2rq
Subscribe Now