The Democratic Republic of Congo (DRC) will proceed with a smaller version of the Inga III hydropower project and expand the facility over time, President Felix Tshisekedi said.
The Inga III dam, which will begin as a 4 800 MWplant, will have its capacity increased to 7 500 MW and 11 000 MW eventually, Tshisekedi told lawmakers Friday in the capital, Kinshasa. Once completed, the facility would be the biggest hydroelectric power station on the continent and provide much-needed electricity to Congo and other nations, including South Africa.
The AfDB financed feasibility studies for the dam when it was envisaged as a 4 800 MW facility, in 2013. However, a year ago, two groups of Spanish and Chinese developers submitted a joint proposal to the government for a 11 050 MWdam that would cost about $14-billion.
The government’s latest model would give “us the latitude to combine some of these phases, given the fact that the demand for this energy is available and very urgent, especially to serve the development of a factory for aluminum electrolytic production,” Tshisekedi said, without elaborating further.
Congolese officials will meet with the AfDB in Ivory Coast before December 20 to sign the agreement, he said.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation