https://www.engineeringnews.co.za

Dolphin economics updated by Group 6 Metals

1st November 2022

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – A review of the Dolphin tungsten mine, in Tasmania, has increased the project’s expected costs, owner Group 6 Metals said this week.

The company said that a detailed review of costs associated with completing construction activities and the working capital requirements to achieve steady state production, amid concerns of rising costs owing to global inflationary pressures, had been undertken.

The review has identified several areas of cost escalation, however, these increased costs are more than offset by sustained higher ammonium paratungstate (APT) prices and favourable foreign exchange rates.

The project’s startup capital costs have increased from the A$72.7-million to A$92.7-million, with deferred capital increasing from A$56.5-million to A$61.2-million, while life-of-mine capital costs have increased from A$129.2-million to A$153.9-million.

However, the review also resulted in a 24% increase in the Dolphin project’s estimated net present value, increasing from A$241-million to A$300-million, while the internal rate of return has declined from 43% to 38%. The capital pay-back has increased slightly from 2.25 years to just under three years.

“Despite the challenges faced by many mining projects under construction over the last 12 months, primarily due to escalating capital and operating costs, logistical challenges and labour shortages, we are very happy with the progress achieved at Dolphin to date and with the updated project financial metrics,” said Group 6 MD and CEO Keith McKnight.

“The net present value for the project has increased significantly from A$241-million to A$300-million pre-tax after factoring in all of these factors.

“The project is tracking well against schedule, with commissioning of the process plant still expected to be completed by the end of March 2023, as all the major OEM equipment has now been delivered to site to complete the construction of the process plant. In parallel, the mine infrastructure is also progressing well with construction of the tailings storage facility underway and expected to be available in March 2023 when needed for commissioning.

“The market fundamentals for tungsten continue to look increasingly positive. There is an anticipated shortage of tungsten concentrate in 2023 due to increasing demand and limited new supply coming online. The price for APT has remained stable at $335/t to A340/t of tungsten, for much of the last six months and given the current Australian/US dollar exchange rate, is the highest APT price in Australian dollar terms since the mine last operated,” said McKnight.

"While there has been cost escalation in capital and operating costs, by overcoming these challenges the company can take advantage of very favourable market conditions to maximise returns from one of the highest-grade tungsten projects in the western world.”

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest News

SKAO director-general Prof Jessica Dempsey
The SKA Observatory has a new head
2nd June 2026 By: Rebecca Campbell

Showroom

Columbus Stainless
Columbus Stainless

Columbus Stainless, based in Middelburg, Mpumalanga, is Africa’s only producer of stainless steel flat products. In addition, Columbus is the only...

VISIT SHOWROOM 
Kriel Occupational Health Centre
Kriel Occupational Health Centre

Occupational health services, mobile clinics, wellness campaigns, aviation.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.174 1.074s - 140pq - 2rq
Subscribe Now