Deflector progressing to schedule
PERTH (miningweekly.com) – Production at the Deflector gold project, in Western Australia, has moved to transition ore, boosting gold and copper recoveries, Doray Minerals has reported.
MD Allan Kelly said on Thursday that the company was pleased with the progress of mining and production ramp-up at Deflector, and was looking forward to the start of production from the primary sulphide ore in the new year.
“As predicted, gold and copper recoveries have increased markedly as we move into the transition ore and we are also seeing some very high-grade sulphide mineralisation being exposed with our first development drives.”
Mining of the openpit is progressing with some 90% complete at the end of October and production has reduced to a single day shift, as the available work area decreased towards the base of the pit.
The pit was now scheduled for completion in early 2017, and Kelly said that the evaluation of a possible southern extension to the pit was ongoing. However, mining of any extensions will be deferred to a later date.
Meanwhile, underground development is also progressing on schedule, with the decline and lateral access advanced 920 m at the end of October.
A total of 200 m of ore drive development within the Western and Central Lodes has been completed to date, in preparation for the start of stoping in early 2017.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation