Cullinan processing plant project, South Africa
Name of the Project
Cullinan processing plant project.
Location
Gauteng, South Africa.
Client
Petra Diamonds (74%), Kago Diamonds (14%) and the Itumeleng Petra Diamonds Employee Share Trust (12%).
Project Description
Petra Diamonds has built a modern, fit-for-purpose processing plant at Cullinan, with a throughput capacity of six-million tonnes a year.
The new plant is expected to improve the recovery of the full spectrum of diamonds, thereby increasing the volume of stones recovered and protecting large stones from breakage. It will also improve the efficiency of the material flow, thereby significantly lowering operating costs and reducing the mine’s environmental footprint.
The new plant incorporates:
• autogenous milling – a gentler recovery process that breaks down ore using attrition rather than crushing, thereby better protecting the large, high-value stones for which the Cullinan mine is known;
• high-pressure grinding rolls technology – a gentler liberation technique incorporating interparticle crushing, thereby moving away from high-impact cone crushing; and
• XRF X-ray technology to replace conventional dense-media separation plants to treat coarser +12 mm material.
The new plant replaces the old plant, which was originally commissioned in 1947, thereby reducing the processing footprint at Cullinan from about 27 ha to an estimated 4 ha, with the associated reduction of engineering infrastructure deployed, including an expected reduction in the number of conveyor belts used from 151 (spanning 15 km) to 22 (spanning 3 km).
The new plant is expected to yield a saving of between R20/t and R25/t in processing costs, owing to increased energy efficiency and improved water consumption, as well as reduced circulation and maintenance requirements.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has an internal rate of return of 25%, with a payback of about three years.
Value
The project is estimated at R1.65-billion to implement.
Duration
The new plant was commissioned during the fourth quarter of the 2017 financial year.
Latest Developments
The Cullinan plant achieved a milestone in the quarter ended December 31, 2017, with the processing of one-million tonnes of run-of-mine (RoM) ore, and further to testwork performed, was assessed to have achieved its nameplate capacity of six-million tonnes, which included RoM and tailings.
Plant optimisation is ongoing.
Key Contracts and Suppliers
MDM Engineering (front-end engineering design), now part of Amec Foster Wheeler.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Petra Diamonds, email info@petradiamonds.com.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation