Eastgate shopping centre to get additional 5.74 MW solar plant

Concor is installing a solar PV plant at the Eastgate shopping centre

Concor is installing a solar PV plant at the Eastgate shopping centre

19th May 2023

By: Schalk Burger

Creamer Media Senior Deputy Editor

     

Font size: - +

Construction contractor Concor is working on a project to build a 5.74 MW solar photovoltaic (PV) power plant in the Eastgate shopping centre’s upper parking area, adding to the centre’s existing 1 MW solar plant.

This project aligns with JSE-listed real estate investment trust Liberty 2 Degrees’ execution of its 2030 net-zero targets, which includes reducing energy reliance on the grid, and a focus on creating good and smart spaces.

This second-phase project, which started in February, will comprise approximately 550 t of structural steel roof constructed on concrete plinths on the upper parking area of the shopping centre, said Concor contract manager Martin Muller.

“We will be constructing concrete columns and steelwork to hold the PV panels on the upper parking level over an area of 31 000 m2. The panels will also create shade for shoppers parking on this level,” he said.

The solar PV project is scheduled for completion by the end of January 2024, Muller said.

The project requires the existing column heads that support the parking deck to be exposed. This will allow Concor to drill and dowel into the column heads so that starter bars can be inserted for the stub columns to be poured, ensuring that the loads are spread onto the main columns below, he explained.

“Special attention is being paid to mitigate any disruption to the shopping centre’s tenants and shoppers. A full mitigation kit will also be applied to keep water out during construction and minimise any impact on the live shopping area below,” he added.

The concrete stub columns, most of which will be two metres in height, will be constructed from 30 MPa readymix concrete. To enhance sustainability, this Green Star-rated concrete will use 30% fly ash to reduce the concrete’s embodied energy.

Concor has executed similar projects in both the retail and commercial office environments, and has also contributed significantly to pioneering wind energy projects around the country.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 
Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.061 0.739s - 122pq - 2rq
Subscribe Now